Skip to content
The Climate Litigation Database

Delaware Riverkeeper Network v. Federal Energy Regulatory Commission

About this case

Filing year
2020
Status
Petition for review denied.
Docket number
20-1206
Court/admin entity
United StatesUnited States Federal CourtsUnited States Court of Appeals for the District of Columbia (D.C. Cir.)
Case category
Federal Statutory Claims (US)NEPA (US)Federal Statutory Claims (US)Other Statutes and Regulations (US)
Principal law
United StatesAdministrative Procedure Act (APA)United StatesFifth Amendment—Due ProcessUnited StatesNational Environmental Policy Act (NEPA)United StatesNatural Gas ActUnited StatesNinth AmendmentUnited StatesTenth Amendment
At issue
Challenge to the Federal Energy Regulatory Commission's approval of the Adelphia Gateway Project, a project involving acquisition of an existing natural gas pipeline system and construction of new lateral pipeline segments and facilities.
Topics
, ,

Documents

Filing Date
Document
Type
Topics 
Beta
Search results
08/02/2022
Petition for review denied.
The D.C. Circuit Court of Appeals denied a petition for review challenging the Federal Energy Regulatory Commission’s (FERC’s) approval of the Adelphia Gateway Project, which involved acquisition of an existing pipeline system in Pennsylvania and Delaware and construction of short lateral pipeline segments and facilities to operate the pipeline. The court rejected contentions that FERC’s analysis of environmental impacts was deficient, including arguments related to the evaluation of the project’s impacts on greenhouse gas emissions and climate change. First, the court found that the petitioners had not identified evidence that would undermine FERC’s conclusion that upstream effects such as new natural gas wells to meet the pipeline’s increased capacity were not reasonably foreseeable. Second, the court found that FERC’s “reasoning was sound” when it concluded that downstream greenhouse gas emissions were not reasonably foreseeable because FERC could not identify the end users. The court cited its precedent that rejected the contention that downstream combustion emissions are reasonably foreseeable impacts of pipeline projects as a categorical matter. Third, the court found that the petitioners had failed to raise before FERC their argument that National Environmental Policy Act (NEPA) regulations required use of the Social Cost of Carbon. The court also rejected other arguments under NEPA, as well as claims regarding the market need for the project and regarding preemption of state and local action.
Decision
03/30/2021
Final answering brief filed for respondent-intervenor Adelphia Gateway, LLC.
Brief
03/30/2021
Reply

Summary

Challenge to the Federal Energy Regulatory Commission's approval of the Adelphia Gateway Project, a project involving acquisition of an existing natural gas pipeline system and construction of new lateral pipeline segments and facilities.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Policy instrument
Risk
Impacted group
Just transition
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance