In re Florida Southeast Connection, LLC

About this case

Filing year
2016
Status
Request filed for expedited issuance of order on remand reissuing certificates, or in the alternative, abbreviated application for temporary emergency certificates.
Docket number
CP14-554-001, CP15-16-001, CP15-17-001
Court/admin entity
United StatesFederal AgenciesFERC
Case category
Federal Statutory ClaimsNEPA
Principal law
United StatesNational Environmental Policy Act (NEPA)
At issue
Challenge to FERC approvals for natural gas pipeline from Alabama to Florida.
Topics
, ,

Documents

Filing Date
Document
Type
Topics 
Beta
Search results
02/02/2018
Request filed for expedited issuance of order on remand reissuing certificates, or in the alternative, abbreviated application for temporary emergency certificates.
Request
09/07/2016
Order issued denying rehearing.
The Federal Energy Regulatory Commission (FERC) denied rehearing of its authorizations for construction and operation of a natural gas pipeline from Alabama to Florida. FERC rejected the organizations’ call for consideration of indirect effects related to induced upstream production and downstream natural gas consumption.
Decision

Summary

Challenge to FERC approvals for natural gas pipeline from Alabama to Florida.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Policy instrument
Risk
Impacted group
Just transition
Renewable energy
Fossil fuel
Greenhouse gas
Economic sector