Skip to content
The Climate Litigation Database

New Jersey Conservation Foundation v. Federal Energy Regulatory Commission

About this case

Filing year
2023
Status
Petitions for review granted, FERC orders vacated, and matter remanded to FERC.
Docket number
23-1064
Court/admin entity
United StatesUnited States Federal CourtsUnited States Court of Appeals for the District of Columbia (D.C. Cir.)
Case category
Federal Statutory Claims (US)NEPA (US)Federal Statutory Claims (US)Other Statutes and Regulations (US)
Principal law
United StatesAdministrative Procedure Act (APA)United StatesNational Environmental Policy Act (NEPA)United StatesNatural Gas Act
At issue
Challenge to Federal Energy Regulatory Commission authorizations for the Regional Energy Access Expansion project, a natural gas infrastructure project to expand natural gas transportation service to New Jersey, Pennsylvania, and Maryland.
Topics
, ,

Documents

Filing Date
Document
Type
Topics 
Beta
Search results
07/30/2024
Petitions for review granted, FERC orders vacated, and matter remanded to FERC.
The D.C. Circuit Court of Appeals vacated FERC orders authorizing the construction and operation of a natural gas pipeline running through New Jersey, New York, Delaware, Maryland, and Pennsylvania. The court found that FERC’s decision “not to make a case-specific determination about the significance of the Project’s anticipated GHG emissions, in light of its own stated precedent that it can do so, nor to explain why it believed it could not do so, was arbitrary and capricious.” The court pointed to the earlier proceeding in which FERC had assessed the significance of greenhouse gas emissions (the same proceeding referenced in Healthy Gulf, above) and said it was unreasonable for FERC not even to acknowledge a change in position. The court also noted that in this case FERC’s “own estimates anticipate that the Project will spur enormous GHG emissions and associated costs” but that FERC declined to label the emissions as significant or insignificant in part based on an ongoing “generic proceeding” to determine whether and how FERC would conduct such determinations. The D.C. Circuit found that FERC did not explain why the pendency of the generic proceeding would affect FERC’s ability to make a case-specific determination as it had in the earlier proceeding. The court said that where FERC did not dispute, as was the case here, that it was “generally obligated to make a significance determination for each category of emissions” and instead argued that it was unable to make such a determination, it was necessary for FERC to provide an explanation. Also under NEPA, the D.C. Circuit found that FERC failed to assess mitigation strategies as required by NEPA regulations. The court rejected other NEPA arguments regarding the need to consider upstream and downstream emissions and the definition of project purpose and need. Under the Natural Gas Act, the court found that FERC acted arbitrarily by failing to respond to “material challenges to its finding of market need.” The court also found that FERC’s public interest determination was arbitrary and capricious both because it relied on the deficient determination of market need and also because it failed to conduct “any meaningful balancing” of potential environmental harms—including harms from increased greenhouse gas emissions—against the project’s benefits.
Decision
03/23/2023
Motion To Intervene
03/22/2023
Opposition to emergency motion for stay filed by intervenor Transcontinental Gas Pipe Line Company, LLC.
Opposition
03/21/2023
Emergency motion for stay filed by petitioners.
On March 21, 2023, one group of petitioners filed an emergency motion to halt construction activities, including tree-felling. The petitioners argued that they were likely to succeed on the merits of their claim that FERC unlawfully approved project, including because FERC did not consider evidence that that there was no need for the project, and that FERC failed to adequately balance the project’s adverse impacts and public benefits. They argued that environmental harms, including impacts on climate change, would cause irreparable injury; that a stay would not significantly harm the applicant or other parties; and that there was “fundamental public interest” in granting a stay, including because the project would increase upstream gas production and contribute to adverse climate impacts.
Motion
03/13/2023
Joint petition for review filed.
Environmental organizations filed petitions for review in the D.C. Circuit Court of Appeals challenging Federal Energy Regulatory Commission (FERC) authorizations for the Regional Energy Access Expansion project, a natural gas infrastructure project that involves modernization of existing compression facilities and construction of new facilities to provide an additional 829,400 dekatherms per day of “firm transportation service” for shippers from northeastern Pennsylvania to delivery points in New Jersey, Pennsylvania, and Maryland.
Petition

Summary

Challenge to Federal Energy Regulatory Commission authorizations for the Regional Energy Access Expansion project, a natural gas infrastructure project to expand natural gas transportation service to New Jersey, Pennsylvania, and Maryland.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Target
Policy instrument
Risk
Impacted group
Just transition
Renewable energy
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance