Skip to content
The Climate Litigation Database

Trustees for the Time Being of the GroundWork Trust v. Minister of Environmental Affairs, KiPower (Pty) Ltd, and Others

Geography
Year
2017
Document Type
Litigation

About this case

Filing year
2017
Status
Decided
Court/admin entity
South AfricaHigh Court
Case category
Suits against governmentsEnvironmental assessment and permittingUtilities
Principal law
South AfricaNational Environmental Management Act 107 of 1998
At issue
Consideration of climate change in environmental impact statements
Topics
, ,

Documents

Summary

The environmental organization groundWork has filed a motion requesting that South Africa’s High Court review and set aside the Department of Environmental Affair’s authorization to develop a 600 MW coal-fired power plant, the “KiPower Project,” without first considering the climate change impacts of the plant. They also challenge the Minister of Environmental Affairs’ decision to dismiss groundWork’s appeal of the authorization. Petitioners argue this dismissal directly contradicts the Court’s decision in EarthLife Africa Johannesburg v. Minister of Environmental Affairs and Others handed down on March 8, 2017. This case considered similar authorization for a 1200 MW coal-fired plant called the Thabametsi Project. In EarthLife Africa Johannesburg, the Court held that “the climate change impacts of a proposed coal-fired power station are required to be assessed and comprehensively considered as part of an environmental impact assessment (“EIA”)” under the National Environmental Management Act 107 of 1998 before an authorization decision is reached. National Environmental Management Act Section 24O(1)(b) further requires consideration of impacts, mitigation measures, and domestic as well as international policy commitments before granting an environmental authorization. In EarthLife Africa Johannesburg, the Court recognized South Africa’s commitments under the Paris Agreement as one of the reasons that climate change is a relevant consideration for the environmental review of a coal-fired power plant. This case is one of two court applications filed by groundWork in September 2017 to oppose new coal-fired power plants in the Mpumalanga Highveld –an air quality priority area. On May 3 2022, the High Court issued an order, by agreement between the parties, confirming that the environmental authorization for the planned 600MW KiPower coal-fired power station had expired.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Target
Policy instrument
Risk
Impacted group
Just transition
Fossil fuel
Greenhouse gas
Economic sector
Public finance actor