Status
Judgment reversed and matter remanded to Superior Court with directions to enter a new judgment denying the writ petition in its entirety.
Docket number
E078241
Court/admin entity
United StatesState CourtsCalifornia Court of Appeals (Cal. Ct. App.)
Case category
State Law Claims (US)State Impact Assessment Laws (US)
Principal law
United StatesCalifornia Environmental Quality Act (CEQA)
At issue
Challenge to the CEQA review for a 201,096-square-foot “warehouse/parcel delivery service building."
Topics
, ,

Documents

Filing Date
Document
Type
Topics 
Beta
Search results
08/15/2024
Judgment reversed and matter remanded to Superior Court with directions to enter a new judgment denying the writ petition in its entirety.
Reversing a trial court, the California Court of Appeal concluded that substantial evidence supported the City of Upland’s finding pursuant to the California Environmental Quality Act that a 201,096-square-foot warehouse/parcel delivery service building would not have significant impacts on greenhouse gas emissions. The appellate court found that substantial evidence both supported the use of a 3,000 metric tons of carbon dioxide equivalent per year (MTCO2e/year) quantitative threshold for significance and showed that the project’s emissions would be below this threshold. The court did not consider the project developer’s alternative arguments that substantial evidence supported use of a 10,000 MTCO2e/year threshold or that consistency with the Upland Climate Action Plan demonstrated that the project would not have significant impacts on greenhouse gas emissions. In addition, the appellate court rejected the petitioner’s claim that the City undercounted the number of vehicles and vehicle trips the project would generate and therefore understated the impact the project would have on traffic, transportation, air quality, and greenhouse gas emissions.
Decision

Summary

Challenge to the CEQA review for a 201,096-square-foot “warehouse/parcel delivery service building."

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Target
Policy instrument
Fossil fuel
Greenhouse gas
Economic sector
Finance