Washington v. Federal Emergency Management Agency

About this case

Filing year
2025
Status
States’ motion for summary judgment denied and government's motion for summary judgment denied.
Docket number
1:25-cv-12006
Court/admin entity
United StatesUnited States Federal CourtsUnited States District of Massachusetts (D. Mass.)
Case category
Constitutional ClaimsOther Constitutional ClaimsFederal Statutory ClaimsOther Statutes and Regulations
Principal law
United States42 U.S.C. § 5133 (Predisaster hazard mitigation)United StatesAdministrative Procedure Act (APA)United StatesAppointments ClauseUnited StatesAppropriations ClauseUnited StatesDisaster Mitigation Act of 2000United StatesDisaster Recovery Reform Act of 2018 (DRRA)United StatesInfrastructure Investment and Jobs Act (IIJA)United StatesSpending Clause
At issue
Challlenge brought by 20 states to the termination of the Building Resilient Infrastructure and Communities (BRIC) pre-disaster mitigation program, which states used for climate resilience projects, and the repurposing of BRIC funds.
Topics
, ,

Documents

Filing Date
Document
Type
Topics 
Beta
Search results
12/11/2025
States’ motion for summary judgment denied and government's motion for summary judgment denied.
The federal district court for the District of Massachusetts held that the Federal Emergency Management Agency’s (FEMA’s) termination of the Building Resilient Infrastructure and Communities (BRIC) program was unlawful. The court called the BRIC program “the largest pre-disaster mitigation program offered through FEMA.” As a threshold matter, the court rejected the federal government’s arguments that the case was not ripe, that the plaintiff states lacked standing, and that sovereign immunity barred the claims. The court also rejected the federal government’s contentions that there had been no final agency action, that states’ claims addressed action committed to agency discretion by law, and that the states sought to compel agency action not required by law. On the merits, the court first found that the “summary termination (without the implementation of any replacement program through which states and local governments can obtain mitigation funding) undoubtedly qualifies as a substantial reduction of FEMA’s mitigation responsibilities” within the scope of the statutory provision prohibiting FEMA from substantially or significantly reducing its authorities, responsibilities, or functions. Second, the court found that the termination violated the Further Consolidated Appropriations Act 2024 by redirecting pre-disaster funds to post-disaster relief grant programs. Third, the court found that FEMA had not provided the states with the minimum level of funding mandated by statute. The court declined to address the states’ argument regarding the legality of the appointments of two FEMA officials. The court further found that the states met their burden of showing irreparable harm and established that the balance of hardships and public interest tilted in their favor. The court therefore granted the states’ request for a permanent injunction enjoining cancellation of the BRIC program “as it is currently constituted by an act of Congress.” The court wrote: “In sum, this is not a case about judicial encroachment on the discretionary authority of the Executive Branch. This is a case about unlawful Executive encroachment on the prerogative of Congress to appropriate funds for a specific and compelling purpose, and no more than that.”
Decision
12/11/2025
Termination of the BRIC program vacated and set aside.
Decision
10/15/2025
Memorandum filed by plaintiffs in support of motion for summary judgment.
Motion For Summary Judgment
08/05/2025
Motion for preliminary injunction allowed.
The federal district court for the District of Massachusetts granted plaintiff states’ motion for a preliminary injunction barring the Federal Emergency Management Agency (FEMA) and other federal defendants from spending funds allocated to the Building Resilient Infrastructure and Communities (BRIC) pre-disaster mitigation program for non-BRIC purposes until the court renders a final judgment.
Decision
07/16/2025
Complaint filed.
Twenty states filed a lawsuit on July 16, 2025 claiming that termination of the Building Resilient Infrastructure and Communities (BRIC) pre-disaster mitigation program and repurposing BRIC funds violates separation of powers and is contrary to law in violation of the Administrative Procedure Act, and that withholding appropriated funds violates separation of powers, the Appropriations Clause, and the Spending Clause, and is also contrary to law in violation of the Administrative Procedure Act. The states also challenged the authority of the acting FEMA Administrators to terminate the BRIC program. In addition, they asserted an equitable ultra vires claim. The states alleged that the shutdown of the program had forced communities across the country “to delay, scale back, or cancel hundreds of mitigation projects depending on this funding,” including climate resilience projects.
Complaint
07/16/2025
Memorandum filed in support of motion for preliminary injunction.
Motion

Summary

Challlenge brought by 20 states to the termination of the Building Resilient Infrastructure and Communities (BRIC) pre-disaster mitigation program, which states used for climate resilience projects, and the repurposing of BRIC funds.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Policy instrument
Risk
Impacted group
Just transition
Fossil fuel
Economic sector
Climate finance