On May 8, 2026, the Brazilian Association of Unions and Associations Representing the Energy Industries (ABRAENERGIAS) filed a Public Civil Action (ACP) with a request for urgent relief, filed by against the Federal Government, the Ministry of Mines and Energy (MME), the National Electric Energy Agency (ANEEL), the Energy Research Company (EPE), and the National System Operator (ONS). The plaintiff argues that the Capacity Reserve Auctions in the form of Power (LRCAPs 2026) were structured in violation of the principles of legality, motivation, tariff moderation, administrative efficiency, and free competition, due to alleged irregularities in the definition of contracted power demand, the formation of ceiling prices, and the regulatory modeling of the auctions. They alleged that the auctions resulted in the contracting of an excessive volume of power, with the potential to generate billions in tariff impacts on consumers and favor market concentration in certain economic agents. They also argued that the adopted model favored the contracting of thermoelectric power plants fueled by fossil fuels, such as natural gas, coal, diesel oil, and fuel oil, to the detriment of less expensive and more environmentally sound technological alternatives. This in turn would contribute to increased greenhouse gas emissions and the worsening of climate change, contradicting the energy transition and decarbonization commitments undertaken by the country. Therefore, they requested an urgent injunction to suspend the approval of the auction results and the signing of the respective Reserve Capacity Contracts (CRCAPs), as well as a declaration of nullity of the administrative and regulatory acts related to the LRCAPs 2026.
In a preliminary ruling, the Court denied the plaintiff's request for urgent relief, on the grounds that the controversy involves a matter of high technical and regulatory complexity related to the LRCAPs 2026, and that at that procedural stage, there were insufficient elements to rebut the presumption of legitimacy of the challenged administrative acts. It also highlighted that any suspension of the bidding processes could have significant systemic, regulatory, and operational impacts, recommending greater caution and prior input from the public entities before a thorough examination of the issue.
In June 2026, the National Electric System Operator (ONS) filed a response, arguing preliminarily the lack of standing of ABRAENERGIAS, due to alleged lack of thematic relevance and because it is a generic association, as well as its own lack of passive standing, given the absence of interference in the final decisions regarding the LRCAPs 2026. On the merits, it argued that its role was limited to the preparation of technical and operational studies intended to support the Granting Authority, not being responsible for the final definition of contracted power, ceiling prices, or the conduct and approval of auctions. It defended the regularity of the bidding processes, the existence of technical grounds for contracting power, and the absence of concrete illegality in the studies carried out. It requested its exclusion from the passive side or, alternatively, the dismissal of the claims.
In July 2026, the Federal Government filed a counterclaim defending the legality and technical regularity of the 2026 LRCAPs (Long-Term Energy Reserves), arguing that the definition of power demand strictly followed the studies of EPE (Energy Research Company) and ONS (National System Operator) (even falling short of the indicated systemic demand), that the revision of the ceiling prices resulted from a mere improvement of economic assumptions (and not from a methodological change), and that the universal sharing of capacity reserve costs, established by Law 14.120/2021, corrects historical distortion and concretizes tariff equality between captive and free consumers. It also invoked the theory of institutional capacities and the Chevron and Chenery doctrines to defend judicial deference to technical-administrative merit, and alleged the absence of the requirements for urgent relief, even pointing to the configuration of reverse periculum in mora, given the risk of serious harm to public order, the economy, and public safety in case of suspension of the bidding process. He requested the termination of the proceedings without a decision on the merits or, alternatively, the dismissal of all claims.
Also in July 2026, the Brazilian National Electric Energy Agency (ANEEL) filed a counterclaim arguing that the central grounds of the action, relating to the definition of contracted power demand, the formation and revision of ceiling prices, and the economic modeling of the bidding processes, concern acts under the exclusive competence of the Ministry of Mines and Energy (Granting Authority), and not the Agency itself, whose role was limited to the operationalization of the auctions (preparation of bidding documents and contract drafts, conducting public sessions and subsequent administrative acts) in strict compliance with the guidelines established by MME Normative Ordinances 118 and 119/2025. It highlighted that the bidding process has already run its regular course, with the homologation and awarding of the contracts, and that the Federal Court of Accounts (TCU) authorized the continuation of the bidding process, confirming the correctness of the previous judicial decisions that denied the request for urgent relief. It requested the complete dismissal of the claims.
- Climate Litigation Database
- /
- Search
- /
- Brazil
- /
- ABRAENERGIAS vs. União Federal e outros (Regulatory flaws in the 2026 energy capacity reserve auctions)
ABRAENERGIAS vs. União Federal e outros (Regulatory flaws in the 2026 energy capacity reserve auctions)
About this case
Filing year
2026
Status
Pending
Geography
🇧🇷 Brazil
Court/admin entity
Brazil → Federal District → Federal District Federal Court
Case category
Suits against governments (Global) → Energy and power (Global)
Principal law
Brazil → Consumer Protection CodeBrazil → Federal Constitution of 1988 → Article 225 of the Federal Constitution (CRFB/88)Brazil → National Policy on Climate Change – PNMC (Federal Law No. 12.187 of 2009)
Topics
, ,
Documents
Each case in our database can contain one or more documents.
Filing Date
Document
Type
Topics
07/21/2026
Reply brief by the ANEEL (in Portuguese).
Reply
Finance flowFossil fuelEnergy supply mitigationRenewable energy+ 10 more
07/09/2026
Reply brief by the Federal Union (in Portuguese).
Reply
Fossil fuelCoalGasFinance flow+ 42 more
06/22/2026
Reply brief by the ONS (in Portuguese).
Reply
Finance flowEnergy supply mitigationRenewable energyEnergy supply sector+ 27 more
06/12/2026
Reply brief by the EPE (in Portuguese).
Reply
Finance flowEnergy storageEnergy supply mitigationRenewable energy+ 19 more
05/08/2026
On May 8, 2026, the Brazilian Association of Unions and Associations Representing the Energy Industries (ABRAENERGIAS) filed a Public Civil Action (ACP) with a request for urgent relief, filed by against the Federal Government, the Ministry of Mines and Energy (MME), the National Electric Energy Agency (ANEEL), the Energy Research Company (EPE), and the National System Operator (ONS). The plaintiff argues that the Capacity Reserve Auctions in the form of Power (LRCAPs 2026) were structured in violation of the principles of legality, motivation, tariff moderation, administrative efficiency, and free competition, due to alleged irregularities in the definition of contracted power demand, the formation of ceiling prices, and the regulatory modeling of the auctions. They alleged that the auctions resulted in the contracting of an excessive volume of power, with the potential to generate billions in tariff impacts on consumers and favor market concentration in certain economic agents. They also argued that the adopted model favored the contracting of thermoelectric power plants fueled by fossil fuels, such as natural gas, coal, diesel oil, and fuel oil, to the detriment of less expensive and more environmentally sound technological alternatives. This in turn would contribute to increased greenhouse gas emissions and the worsening of climate change, contradicting the energy transition and decarbonization commitments undertaken by the country. Therefore, they requested an urgent injunction to suspend the approval of the auction results and the signing of the respective Reserve Capacity Contracts (CRCAPs), as well as a declaration of nullity of the administrative and regulatory acts related to the LRCAPs 2026.
In a preliminary ruling, the Court denied the plaintiff's request for urgent relief, on the grounds that the controversy involves a matter of high technical and regulatory complexity related to the LRCAPs 2026, and that at that procedural stage, there were insufficient elements to rebut the presumption of legitimacy of the challenged administrative acts. It also highlighted that any suspension of the bidding processes could have significant systemic, regulatory, and operational impacts, recommending greater caution and prior input from the public entities before a thorough examination of the issue.
In June 2026, the National Electric System Operator (ONS) filed a response, arguing preliminarily the lack of standing of ABRAENERGIAS, due to alleged lack of thematic relevance and because it is a generic association, as well as its own lack of passive standing, given the absence of interference in the final decisions regarding the LRCAPs 2026. On the merits, it argued that its role was limited to the preparation of technical and operational studies intended to support the Granting Authority, not being responsible for the final definition of contracted power, ceiling prices, or the conduct and approval of auctions. It defended the regularity of the bidding processes, the existence of technical grounds for contracting power, and the absence of concrete illegality in the studies carried out. It requested its exclusion from the passive side or, alternatively, the dismissal of the claims.
In July 2026, the Federal Government filed a counterclaim defending the legality and technical regularity of the 2026 LRCAPs (Long-Term Energy Reserves), arguing that the definition of power demand strictly followed the studies of EPE (Energy Research Company) and ONS (National System Operator) (even falling short of the indicated systemic demand), that the revision of the ceiling prices resulted from a mere improvement of economic assumptions (and not from a methodological change), and that the universal sharing of capacity reserve costs, established by Law 14.120/2021, corrects historical distortion and concretizes tariff equality between captive and free consumers. It also invoked the theory of institutional capacities and the Chevron and Chenery doctrines to defend judicial deference to technical-administrative merit, and alleged the absence of the requirements for urgent relief, even pointing to the configuration of reverse periculum in mora, given the risk of serious harm to public order, the economy, and public safety in case of suspension of the bidding process. He requested the termination of the proceedings without a decision on the merits or, alternatively, the dismissal of all claims.
Also in July 2026, the Brazilian National Electric Energy Agency (ANEEL) filed a counterclaim arguing that the central grounds of the action, relating to the definition of contracted power demand, the formation and revision of ceiling prices, and the economic modeling of the bidding processes, concern acts under the exclusive competence of the Ministry of Mines and Energy (Granting Authority), and not the Agency itself, whose role was limited to the operationalization of the auctions (preparation of bidding documents and contract drafts, conducting public sessions and subsequent administrative acts) in strict compliance with the guidelines established by MME Normative Ordinances 118 and 119/2025. It highlighted that the bidding process has already run its regular course, with the homologation and awarding of the contracts, and that the Federal Court of Accounts (TCU) authorized the continuation of the bidding process, confirming the correctness of the previous judicial decisions that denied the request for urgent relief. It requested the complete dismissal of the claims.
Complaint
Fossil fuelPublic sectorFinance flowEnergy supply mitigation+ 29 more
Summary
Topics mentioned most in this case
See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.
Group
Topics
Target
Policy instrument
Risk
Impacted group
Just transition
Renewable energy
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance