About this case
Filing year
2026
Status
Petition for review filed.
Geography
Docket number
26-1261
Court/admin entity
United States → United States Federal Courts → United States Court of Appeals for the Ninth Circuit (9th Cir.)
Case category
Federal Statutory Claims (US) → NEPA (US)Federal Statutory Claims (US) → Other Statutes and Regulations (US)
Principal law
United States → Administrative Procedure Act (APA)United States → Federal Power ActUnited States → National Environmental Policy Act (NEPA)
At issue
Challenges to the the U.S. Department of Energy’s December 16, 2025 order requiring that a coal-fired generation unit at the TransAlta Central Generation electric generating facility in Washington continue to be made available for operation.
Topics
, ,
Documents
Filing Date
Document
Type
Topics
Beta
Search results
03/04/2026
Petition for review filed.
Five environmental organizations filed a petition for review in the Ninth Circuit Court of Appeals challenging the U.S. Department of Energy’s (DOE's) December 16, 2025 order requiring that a coal-fired generation unit at the TransAlta Central Generation electric generating facility in Centralia, Washington, be made available for operation until March 16, 2026. The unit had been slated to cease operation in December 2025. The Secretary of Energy declared that an emergency existed in the Western Electricity Coordinating Council Northwest assessment area resulting from increasing demand and accelerated retirement of generation facilities. The environmental organizations’ request for rehearing argued that the order violated the Federal Power Act, including because DOE did not ensure the order was consistent with state environmental laws to the maximum extent practicable, including laws governing the plant’s greenhouse gas emissions.
Petition
–
Summary
Challenges to the the U.S. Department of Energy’s December 16, 2025 order requiring that a coal-fired generation unit at the TransAlta Central Generation electric generating facility in Washington continue to be made available for operation.
Topics mentioned most in this case Beta
See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more