17-17152, 17-17252, 17-17263United States Court of Appeals for the Ninth Circuit (9th Cir.)3 entries
Filing Date
Document
Type
12/21/2017
Appellants' joint motion to dismiss appeals granted.
Decision
12/12/2017
Joint motion to dismiss appeals filed.
Motion
01/01/2014
Filed
Center for Biological Diversity v. U.S. Bureau of Land Management ↗
2:14-cv-00226United States District Court for the District of Nevada (D. Nev.)5 entries
Filing Date
Document
Type
11/03/2017
Notice of cross-appeal filed by plaintiffs.
Appeal
11/02/2017
Notice of appeal filed by defendant-intervenor Southern Nevada Water Authority.
Appeal
10/20/2017
Notice of appeal filed by federal defendants.
Appeal
08/23/2017
Order issued granting in part and denying in part the parties' motions for summary judgment.
The federal district court for the District of Nevada largely upheld approvals for the first phase of “a massive water-redistribution pipeline” intended to carry millions of gallons of water to Nevada’s most populous county, including by rejecting the plaintiff’s argument that the U.S. Bureau of Land Management (BLM) did not take a hard look at the extent to which climate change might amplify the project’s environmental impacts. The court found that BLM adequately considered climate change impacts by generally considering global climate change and regional climate change trends. The court rejected the plaintiffs’ contention that BLM’s assessment should have included specific climate change data, finding that the plaintiffs had failed to point to any “hard data” that BLM should have included in its analysis. The court also agreed with BLM that new climate change studies indicating an increased risk of drought in the Southwest did not warrant preparation of a supplemental environmental impact statement (EIS). The court concluded that the studies provided “no new, raw data about how climate change might affect the pipeline’s environmental impact” and that BLM had already qualitatively considered the studies’ conclusions in its EIS.
Decision