- In re Hawaiian Electric Co.
Collection
In re Hawaiian Electric Co.
In re Hawaiian Electric Co. ↗
SCOT-20-0000309Haw., State Courts1 entry
Filing Date
Type
Action Taken
Document
Summary
06/29/2021
Decision
Public Utilities Commission order affirmed.
The Hawai‘i Supreme Court held that the state’s Public Utilities Commission (PUC) did not abuse its discretion when it declined to re-open a 2014 order that approved a Purchase Power Agreement for wind energy. One of the allegations made by the nonprofit organization that sought to re-open the order was that the 2014 order did not analyze the project’s impact on greenhouse gas emissions as required by the public utilities law. The court found that the PUC properly declined to re-open the order to address this issue since the organization could have raised the issue earlier since the absence of an analysis of greenhouse gas emissions was “readily apparent.”