About this case

Documents

Filing Date
Type
Action Taken
Document
Summary
07/21/2008
Decision
Dismissal of citizen suit affirmed.
Environmental groups brought a citizen suit against several utility entities to enjoin their construction of a pulverized coal-fired power plant in their community, based on various violations of the preconstruction permit process of the Clean Air Act. The district court dismissed the suit for lack of subject matter jurisdiction, holding that held that Sections 7604(a)(1) and (a)(3) did not authorize citizen suits to redress alleged pre-permit, preconstruction, pre-operation Clean Air Act violations. The Fifth Circuit upheld the district court's decision.

Summary

Citizen suit against companies seeking air permits for coal-fired power plant project in Texas.