- Climate Litigation Database
- /
- Search
- /
- United States
- /
- California
- /
- Desert Protection Society v. Haaland
Desert Protection Society v. Haaland
Geography
Year
2019
Document Type
Litigation
Part of
About this case
Filing year
2019
Status
Defendants' and intervenor-defendants' motions for summary judgment granted and plaintiff's motion for summary judgment denied.
Geography
Docket number
2:19-cv-00198
Court/admin entity
United States → United States Federal Courts → United States District Court for the Eastern District of California (E.D. Cal.)
Case category
Federal Statutory Claims (US) → NEPA (US)Federal Statutory Claims (US) → Other Statutes and Regulations (US)
Principal law
United States → Administrative Procedure Act (APA)United States → Federal Land Policy and Management Act (FLPMA)United States → National Environmental Policy Act (NEPA)
At issue
Challenge to the National Environmental Policy Act review in connection with a right-of-way for an electrical line and water supply pipeline for a pumped storage electrical generation project.
Topics
, ,
Documents
Filing Date
Document
Type
Topics
Beta
09/29/2023
Defendants' and intervenor-defendants' motions for summary judgment granted and plaintiff's motion for summary judgment denied.
The federal district court for the Eastern District of California found that the U.S. Bureau of Land Management (BLM) complied with the National Environmental Policy Act (NEPA) in connection with its granting of a right-of-way for an electrical line and water supply pipeline for a pumped storage electrical generation project (the energy project) near Joshua Tree National Park. The Federal Energy Regulatory Commission (FERC) approved the energy project in 2014 after completing an environmental impact statement (EIS). BLM “tiered” its NEPA review to FERC’s EIS. The court rejected arguments that BLM failed to address global warming’s impacts on groundwater, noting that only the energy project—not the right-of-way—would have an impact on groundwater usage, and that BLM therefore was not required to conduct additional analysis regarding the energy project’s impacts on groundwater. The court noted that BLM nevertheless had reviewed “more up-to-date information on climate change” and found that annual precipitation was not anticipated to change despite global warming. The court also stated that by asserting that BLM had a duty “to separately address the way global warming might intensify the effects of the Project,” plaintiff “misunderstands what NEPA requires.” The court said that “NEPA requires that an agency must assess the impacts of the project on the environment, not the other way around.” The court found that the plaintiff did not contend the right-of-way would have an impact on global warming, only that global warming would increase the project’s other impacts. The court further found that to the extent the plaintiff claimed BLM failed to address how global warming would intensify the project’s impacts on groundwater overdraft and wildlife, BLM had conducted sufficient analysis. In addition, the court found no violations of the Federal Land Policy and Management Act or the Administrative Procedure Act.
Decision
Summary
Challenge to the National Environmental Policy Act review in connection with a right-of-way for an electrical line and water supply pipeline for a pumped storage electrical generation project.
Topics mentioned most in this case Beta
See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more
Group
Topics
Policy instrument
Risk
Impacted group
Renewable energy
Fossil fuel
Economic sector
Adaptation/resilience
Finance