On May 18, 2026, the Federation of Industries of the State of Ceará (FIEC) and the Union of Energy and Services Industries of the Electric Sector of the State of Ceará (SINDENERGIA) filed a Public Civil Action (ACP) with a request for urgent relief, against the Federal Government, the National Electric Energy Agency (ANEEL), the Energy Research Company (EPE), and the National System Operator (ONS). Plaintiffs allege that the Capacity Reserve Auction (LRCAP) 2026 compromises competitiveness and economic rationality, shows signs of methodological inconsistencies, may impact the tariff formation of the electricity sector, and is inconsistent with environmental protection and sustainable development, thus violating the international climate commitments assumed by Brazil. With the estimated cost of contracting through LRCAP being over R$ 500 billion, in addition to an increase in consumer tariffs in general, significant effects on the industrial sector are anticipated. Plaintiffs argue that the energy sector should evaluate more efficient, competitive, and sustainable technologies, considering solutions already discussed in the international market.
Plaintiffs claim that the demand does not intend to replace technical and administrative merit, but to verify the legal, procedural, regulatory, and competitive compliance of the administrative acts carried out within the scope of LRCAP 2026. This attention should be paid given the long duration of the contracts signed, the potential billion-dollar tariff impacts, and the systemic relevance of the electricity sector to the national economy. FIEC and SINDENERGIA argue that the adopted model is questionable regarding the technological neutrality and environmental compatibility of the promoted expansion, since the auctions are prioritizing the contracting of fossil fuel thermoelectric sources, such as coal, to the detriment of more efficient and sustainable alternatives. They argue that the auction threatens the environmental protection foreseen in Article 225 of the Federal Constitution and in the National Policy on Climate Change, which establishes the inclusion of the climate agenda in national energy policies. An urgent injunction is requested to suspend the acts of approval, awarding, and formalization of the Capacity Reserve Power Contracts arising from LRCAP 2026 or, alternatively, to suspend the effects of acts related to thermoelectric products. On the merits, a declaration of nullity is requested for the administrative and regulatory acts related to LRCAPs 2026.
In its preliminary ruling, the 1st Federal Court of Ceará found Plaintiff's arguments as involving significant amounts that could compromise the financial stability of companies and families and the clean energy matrix for national energy production, and granted the request for urgent relief to immediately suspend the approval of the results of the LRCAPs 2026 and the signing of the respective contracts. Additionally, it recognized the connection with Public Civil Action No. 1048511-21.2026.4.01.3400 and transferred jurisdiction to the 6th Court of the Federal District, which heard the related lawsuit.
The 6th Court of the Federal District dismissed the preliminary injunction request and declared the previous provisional decision null and void.
In June 2026, the Energy Research Company (EPE) filed a reply, requesting the complete dismissal of the claims, arguing that the energy planning it conducts is based on a professional and meritocratic institutional structure that ensures the impartiality and objectivity of the methodologies used to calculate demand and ceiling prices. It maintained that the power contracting was not excessive or arbitrary and that there was no confusion between energy and power contracting. It alleged that the technical studies prepared by EPE and ONS presented the premises, methodology, and results of the power requirement calculations to support the LRCAP 2026, and that its technical contribution to the formulation of the economic bases of the ceiling prices occurred within the scope of the Ministry of Mines and Energy's (MME) responsibilities. In this context, it stated that the alteration of the ceiling prices sought to avoid short-term contractual uncovered capacity and risks of delays in the medium term. EPE also argued that there is no double remuneration between Fixed Revenue and CVU (Variable Cost of Use) and stated that the analysis of tariff moderation cannot be limited to the nominal comparison of ceiling prices or the gross sum of contractual revenues. It further argued that one cannot conclude that there is a lack of competition solely because of the reduced discount or the concentration of winners, considering incomplete the allegations that the LRCAP 2026 (Brazilian Consumer Price Index) would imply increased costs for the consumer and that the 5.52% discount would indicate weak competition. Regarding the existence of technological alternatives, such as battery storage systems and demand response programs, it argued that their availability does not invalidate the LRCAPs 2026. Finally, it alleged that the lawsuit seeks to shift the examination of issues inherent to energy planning to the Judiciary, an activity attributed to the Ministry of Mines and Energy (MME) and subject to technical-discretionary criteria, and that any declaration of nullity of the LRCAPs 2026 would produce serious consequences for the public interest and national energy security.
In the same month, the Union filed a reply, in which it requested, preliminarily, the recognition of lis pendens with Public Civil Action No. 1048511-21.2026.4.01.3400, with the consequent dismissal of the present action and, subsidiarily, the recognition of the connection between the claims. On the merits, it requested the total dismissal of the claims and the condemnation of the plaintiff to pay the costs of the proceedings, arguing that the definition of the guidelines and regulation of the LRCAPs 2026 falls within the regular exercise of the legal powers of the MME. It argued that the contracting of power constitutes a technical response to the current conditions of the electrical system, notably in view of the expansion of intermittent renewable sources and the expected termination of thermoelectric power plant contracts between 2026 and 2030, allowing the preservation, in the short term, of firm capacity through the use of existing generation infrastructure. Furthermore, it argued that there was no nullity in the preparatory acts and the 2026 LRCAPs, and defended the legality of defining the amount of reserve capacity to be contracted, as well as its respective allocation through the Power Charge for Reserve Capacity (ERCAP), regulated by ANEEL and applicable to consumers in proportion to their consumption. It maintained that defining the volume of energy security constitutes a technical choice, and that deference to the Administration's decisions should be observed, without the Judiciary substituting the administrator's technical judgment. Similarly, it stated that the revision of the ceiling prices of the 2026 LRCAP did not constitute an illegal methodological alteration or administrative casuistry, as EPE observed the pre-established methodology. Furthermore, it dismissed the allegation of distortion in the composition of the CVU (Variable Cost of Use) and argued that the technical requirements of the bidding process did not restrict supply or competition, and that there is no prohibition on the participation of projects belonging to the same economic group in public auctions in the electricity sector. The Union also defended that the mechanisms foreseen in the bidding process are sufficient to mitigate the risk of participation by "paper generators" and that the eventual contracting of thermoelectric plants in the LRCAP 2026 (Brazilian Electricity Regulatory Framework for the 2026 Electricity Sector) can constitute a transitional instrument for managing energy security, compatible with the gradual transition strategy foreseen in the PNTE (National Energy Policy) and with the commitments assumed by Brazil under the Paris Agreement. It argued that the contracting does not, in itself, imply a less favorable outcome for the consumer. It also stated that the design of the LRCAP ensures the participation of different thermoelectric technologies under equal conditions. Finally, it alleged that the technical and regulatory choices that guided the LRCAPs 2026 are compatible with the constitutional mandates related to sustainable development. Regarding the request for urgent relief, it was argued that the requirements for granting it were not met and that granting it posed systemic risks to the public interest.
In August 2026, the National Electric System Operator (ONS) filed a reply, in which it preliminarily requested recognition of its lack of standing to be sued. On the merits, it requested the complete dismissal of the claims, arguing that the LRCAPs (Long-Term Renewable Energy Capacity Contracts) constitute a technically sound regulatory response based on studies prepared by the ONS and EPE (Energy Research Company), intended to ensure sufficient operational reserve to meet peak demand, mitigate the effects of intermittency in renewable sources, and preserve national energy security, avoiding scenarios of power deficit, rationing, or interruption of electricity supply. It argued that the definition of the amount of power to be contracted observes rigorous technical criteria. It stated that the technical studies indicate risk levels incompatible with the reliability standards established by the National Energy Policy if there is no additional contracting of reserve capacity, and that the allegations of overestimation of demand or adoption of excessively conservative scenarios lack technical support or empirical evidence. Furthermore, it highlighted that the definition of the power amount by the Granting Authority was preceded by technical analyses from the ONS (National System Operator) and EPE (Energy Research Company) and submitted by ANEEL (National Agency of Electric Energy) to public consultations, with the participation of interested parties and observance of applicable legal provisions. It also argued that the amounts actually contracted in the LRCAPs 2026 (Long-Term Contracts for Energy and Power Generation) were not unduly increased, being adequate to the technical studies prepared by the ONS and EPE, and that, in reality, the contracting fell short of the systemic need identified in said studies. According to the ONS, the contracting constitutes a necessary response to the transformation of the Brazilian electricity matrix, marked by the expansion of intermittent sources and the reduction of hydroelectric regulation capacity. Finally, it stated that the suspension or annulment of the LRCAPs 2026 could represent a risk to the operation of the SIN (National Interconnected System), with the possibility of power deficits and impacts on the supply of electricity, constituting, in its understanding, a reverse hazard of high gravity.
- Climate Litigation Database
- /
- Search
- /
- Brazil
- /
- FIEC and SINDENERGIA vs. União Federal and others (Irregularities in Energy Capacity Reserve Auctions)
FIEC and SINDENERGIA vs. União Federal and others (Irregularities in Energy Capacity Reserve Auctions)
About this case
Filing year
2026
Status
Pending
Geography
🇧🇷 Brazil
Court/admin entity
Brazil → Federal District → Federal District Federal Court
Case category
Suits against governments (Global) → Energy and power (Global)
Principal law
Brazil → Federal Constitution of 1988 → Article 225 of the Federal Constitution (CRFB/88)Brazil → National Policy on Climate Change – PNMC (Federal Law No. 12.187 of 2009)
Topics
, ,
Documents
Each case in our database can contain one or more documents.
Filing Date
Document
Type
Topics
08/03/2026
Reply brief by the ONS (in Portuguese).
Reply
Finance flowEnergy supply mitigationRenewable energyEnergy supply sector+ 20 more
06/28/2026
Reply brief by the Federal Union (in Portuguese).
Reply
Fossil fuelCoalGasEnergy supply mitigation+ 37 more
06/16/2026
Reply brief by the EPE (in Portuguese).
Reply
Finance flowEnergy supply mitigationRenewable energyPublic sector+ 19 more
05/18/2026
Complaint
Fossil fuelFinance flowPublic sectorEnergy storage+ 18 more
Summary
Topics mentioned most in this case
See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.
Group
Topics
Target
Policy instrument
Risk
Impacted group
Just transition
Renewable energy
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance