- Friends of the Chattahoochee, Inc. v. Couch
Litigation
Friends of the Chattahoochee, Inc. v. Couch
Date
2008
Geography
About this case
Documents
Filing Date
Type
Action Taken
Document
Summary
06/30/2008
Decision
Order issued vacating final decision of administrative law judge.
The Georgia Superior Court rejected a state permit for construction of a coal-fired power plant on the Chattahoochee River. The court held that the Environmental Protection Division of the Georgia Department of Natural Resources must limit the amount of carbon dioxide from the proposed plant before construction can begin, overruling an administrative law judge's decision upholding the agency's approval of the plant.
Summary
Challenge to permit for 1,200 MW coal-fired power plant.