In re Enbridge Energy, LP

Geography
Year
2018
Document Type
Litigation
Part of

About this case

Filing year
2018
Status
Commission's adequacy decision reversed and remanded.
Geography
Docket number
A18-1283
Court/admin entity
United States → State Courts → Minnesota Court of Appeals (Minn. Ct. App.)
Case category
State Law Claims (US) → Utility Regulation (US)
Principal law
United States → Minnesota Public Utilities Commission Regulations
At issue
Application for replacement oil pipeline in Minnesota.
Topics
, ,  

Documents

Each case in our database can contain one or more documents.

Filing Date
Document
Type
Topics
06/03/2019
Commission's adequacy decision reversed and remanded.
The Minnesota Court of Appeals reversed the Public Utilities Commission’s determination that the final environmental impact statement (FEIS) for the proposed Enbridge Line 3 oil pipeline project was adequate. Although the court upheld the Commission’s conclusion that the consideration of many issues, including upstream greenhouse gas emissions, was adequate, the court found that the FEIS was inadequate because it did not address the potential impact of an oil spill into the Lake Superior watershed.
Decision
Fossil fuelOilTechnological impactChemical impact+ 21 more

Summary

Application for replacement oil pipeline in Minnesota.

 Topics mentioned most in this case

See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.

Group
Topics
Policy instrument
Risk
Impacted group
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance