09/02/2014
Decision
Review denied.
The EPA Environmental Appeals Board (EAB) denied a petition seeking review of a Clean Air Act <a href="https://climatecasechart.com/case/in-re-petition-of-footprint-power-salem-harbor-development-lp-for-approval-to-construct-a-bulk-generating-facility-in-the-city-of-salem-massachusetts/">permit</a> for a natural gas-fired power plant in Massachusetts. The EAB concluded, among other findings, that the Massachusetts Department of Environmental Protection had properly set the greenhouse gas "best available control technology" limit.
Summary
Challenge to Clean Air Act permit for natural gas-fired power plant in Massachusetts.