Skip to content
The Climate Litigation Database

In re Unión Fenosa Generación, S.A., Judgment No. 6903/2008 of Sept. 30, 2008

Geography
🇪🇸 Spain
Year
2004
Document Type
Litigation

About this case

Filing year
2004
Status
Denied
Geography
🇪🇸 Spain
Court/admin entity
Spain → Supreme Court of Spain → Administrative Litigation Division
Case category
Suits against governments (Global) → GHG emissions reduction and trading (Global) → EU ETS (Global)
Principal law
Spain → Royal Decree Law 5/2004 of August 27
Topics
, ,  

Documents

Each case in our database can contain one or more documents.

Filing Date
Document
Type
Topics
09/30/2008
An energy company, Unión Fenosa Generación, S.A., brought suit against a decision of the Council of Ministers of Spain of January 21, 2005, whereby it approved the assignment of emissions allowances to two of the company’s power plants for the 2005-2007 term under the provisions of Royal Decree 5/2004 of August 27th, which regulated the market for GHG emissions trading. The Court granted plaintiff’s request for an increase in the emission allowances for its combined cycle power plant in Huelva, which had been incorrectly considered a “new entrant” to the emissions market under the regulation’s timetable. Plaintiff’s request for an increase in its emission allowances as to its coal-fired power plant in La Coruña, one of the five worst emitters in the country¸ was denied. The Court found that the government was justified in applying the maximum penalty of 55% over the total 2000-2002 historical emissions for that category of emitter, despite the fact that plaintiff was thus allowed a lower emission factor than other emitters of the same generation of technologies.
Decision
Tradable permitFinance flowGreenhouse gasManufacturing sector+ 9 more

Summary

An energy company, Unión Fenosa Generación, S.A., brought suit against a decision of the Council of Ministers of Spain of January 21, 2005, whereby it approved the assignment of emissions allowances to two of the company’s power plants for the 2005-2007 term under the provisions of Royal Decree 5/2004 of August 27th, which regulated the market for GHG emissions trading. The Court granted plaintiff’s request for an increase in the emission allowances for its combined cycle power plant in Huelva, which had been incorrectly considered a “new entrant” to the emissions market under the regulation’s timetable. Plaintiff’s request for an increase in its emission allowances as to its coal-fired power plant in La Coruña, one of the five worst emitters in the country¸ was denied. The Court found that the government was justified in applying the maximum penalty of 55% over the total 2000-2002 historical emissions for that category of emitter, despite the fact that plaintiff was thus allowed a lower emission factor than other emitters of the same generation of technologies.

 Topics mentioned most in this case

See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.

Group
Topics
Policy instrument
Risk
Fossil fuel
Greenhouse gas
Economic sector
Finance