INEOS Köln GmbH v Republic of Germany

Geography
International
Year
2016
Document Type
Litigation

About this case

Filing year
2016
Status
Decided
Geography
International
Court/admin entity
European Union → European Court of Justice
Case category
Suits against governments (Global) → GHG emissions reduction and trading (Global) → EU ETS (Global)
Principal law
European Union → Secondary Law → Directives → 2003/87/EC → Regulations → Commission Decision 2011/278/EU
Topics
, ,  

Documents

Each case in our database can contain one or more documents.

Filing Date
Document
Type
Topics
02/22/2018
INEOS operates an installation that produces chemical products and that has been subject to compulsory emissions trading since 2008 through the EU Emissions Trading System (EU ETS). On 23 January 2012, INEOS applied to the German Emissions Trading Authority, within the prescribed time limit, for free allocation of emission allowances for their installation for the period 2013-2020. Later, INEOS challenged the German Authority’s decision about how many free emissions allocations to award the company, claiming that it had not considered data relating to direct emissions for 2006 and 2007, which it was required to do. The German Authority claimed it was not required to consider that data, because it had been submitted after the deadline for the initial application. On 29 September 2015, INEOS brought an action against that decision before the Berlin Administrative Court. The company argued that it had inadvertently omitted to submit certain data, wrongly assuming that the Authority already had that data. Ineos added that the Authority was under an obligation to ask it to supplement or correct the data provided for the purposes of the allocation application. The Administrative Court of Berlin referred to the ECJ a question regarding the interpretation of Article 10(a) of Directive 2003/87/CE and the provisions of Decision 2011/278: must it be interpreted as precluding national legislation which lays down, for the submission of an application for the free allocation of emission allowances for the period 2013-2020, a deadline by which an applicant must correct or complete its application where such shortcomings were only established after the expiry of the time limit? The ECJ ruled that Directive 2003/87/EC and Decision 2011/278 must not be interpreted as precluding such a national provision and that Germany could impose such a deadline because the time limits did not make it practically impossible or excessively difficult to exercise the rights conferred by EU law.
Decision
Tradable permitGreenhouse gasFinance flowDue diligence+ 6 more
11/23/2017
Decision
Tradable permitGreenhouse gasFinance flowTransportation and logistics sector+ 11 more
11/14/2016
Other
Tradable permitGreenhouse gas

Summary

INEOS operates an installation that produces chemical products and that has been subject to compulsory emissions trading since 2008 through the EU Emissions Trading System (EU ETS).

On 23 January 2012, INEOS applied to the German Emissions Trading Authority, within the prescribed time limit, for free allocation of emission allowances for their installation for the period 2013-2020. Later, INEOS challenged the German Authority’s decision about how many free emissions allocations to award the company, claiming that it had not considered data relating to direct emissions for 2006 and 2007, which it was required to do. The German Authority claimed it was not required to consider that data, because it had been submitted after the deadline for the initial application.

On 29 September 2015, INEOS brought an action against that decision before the Berlin Administrative Court. The company argued that it had inadvertently omitted to submit certain data, wrongly assuming that the Authority already had that data. Ineos added that the Authority was under an obligation to ask it to supplement or correct the data provided for the purposes of the allocation application. The Administrative Court of Berlin referred to the ECJ a question regarding the interpretation of Article 10(a) of Directive 2003/87/CE and the provisions of Decision 2011/278: must it be interpreted as precluding national legislation which lays down, for the submission of an application for the free allocation of emission allowances for the period 2013-2020, a deadline by which an applicant must correct or complete its application where such shortcomings were only established after the expiry of the time limit?

The ECJ ruled that Directive 2003/87/EC and Decision 2011/278 must not be interpreted as precluding such a national provision and that Germany could impose such a deadline because the time limits did not make it practically impossible or excessively difficult to exercise the rights conferred by EU law.

 Topics mentioned most in this case

See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.

Group
Topics
Target
Policy instrument
Fossil fuel
Greenhouse gas
Economic sector
Finance