League of Wilderness Defenders/Blue Mountains Biodiversity Project v. Connaughton

About this case

Filing year
2012
Status
Remanded to district court for entry of a preliminary injunction.
Docket number
13-35653
Court/admin entity
United States → United States Federal Courts → United States Court of Appeals for the Ninth Circuit (9th Cir.)
Case category
Federal Statutory Claims (US) → NEPA (US)
Principal law
United States → National Environmental Policy Act (NEPA)
At issue
Challenge to vegetation management program in Oregon.
Topics
, ,  

Documents

Filing Date
Document
Type
Topics 
Beta
05/08/2014
Remanded to district court for entry of a preliminary injunction.
The Ninth Circuit Court of Appeals affirmed in part and reversed in part and remanded for entry of a preliminary injunction. The Ninth Circuit held that plaintiffs were likely to succeed on their claim that the EIS did not adequately discuss the project’s impacts on elk habitat. A supplemental EIS was therefore required.
Decision

Summary

Challenge to vegetation management program in Oregon.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Policy instrument
Risk
Just transition
Economic sector
Adaptation/resilience
Finance