Mullaley Gas and Pipeline Accord Inc v Santos NSW (Eastern) Pty Ltd

Geography
Year
2020
Document Type
Litigation

About this case

Filing year
2020
Status
Decided
Court/admin entity
AustraliaNew South WalesLand and Environment Court
Case category
Suits against corporations, individuals (Global)Corporations (Global)Environmental assessment and permitting (Global)
Principal law
AustraliaEnvironmental Planning and Assessment Act 1979 (NSW)AustraliaLand and Environment Court Act (1979)AustraliaThe State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) 2007
At issue
Whether the Independent Planning Commission properly assessed the climate impacts of a new coal seam gas field.
Topics
, ,

Documents

Summary

The Mullaley Gas and Pipeline Accord (MGPA) community action group brought judicial review proceedings challenging the decision of the Independent Planning Commission (IPC) to grant development consent to the Narrabri Gas Project proposed by Santos NSW (Eastern) Pty Ltd (Santos). The Project proposes the development of a new coal seam gas field and associated infrastructure over 95,000ha in Narrabri in north-western New South Wales. The Project will include the construction of up to 850 gas wells and up to 425 well pads over approximately 25 years and gas processing and water treatment facilities. The approval was based on a “State significant” development status under section 4.36 of the Environmental Planning and Assessment Act 1979 (NSW) (EPA Act), because it supports petroleum production. On September 30, 2020, the IPC approved Santos NSW’s SSD 6456 application. MGPA argued that the IPC failed to properly assess the impacts of the project’s greenhouse gas (GHG) emissions. MGPA challenges two aspects of the IPC’s rationale: (i) its assessment of the expected GHG emissions advantage compared to coal and (ii) its determination that the downstream GHG emissions (Scope 3) are outside the direct control of Santos and therefore not able to be reasonably conditioned. The judicial review proceeding filed by MGPA was heard in the NSW Land and Environment Court in August 2021. On October 18, 2021, the court dismissed the legal challenge to the IPC approval of the Narrabri Gas Project. The court found that MGPA had not established that (i) the IPC erred to consider the expected GHG emissions, relevant to section 4.15(1)(b) of the EPA Act, and (ii) since the Scope 3 emissions were inside Santos’ direct control, the IPC’s decision to exclude these conditions was unreasonable. The Court further found that the IPC did not fail to consider the impacts of any potential gas transmission pipeline into consideration in its determination of the development application for the project, relevant to section 4.15(1)(b), because “the impacts of any potential gas transmission pipeline were sufficiently remote in the chain of likely consequences as not to be likely impacts of the project.”

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Policy instrument
Risk
Impacted group
Fossil fuel
Greenhouse gas
Economic sector
Finance