Skip to content
The Climate Litigation Database

National Wildlife Refuge Association v. Rural Utilities Service

About this cases

Filing year
2024
Status
Federal defendants' and intervenor-defendants' motions for summary judgment granted.
Docket number
3:24-cv-00139
Court/admin entity
United StatesUnited States Federal CourtsW.D. Wis.
Case category
Federal Statutory ClaimsNEPAFederal Statutory ClaimsOther Statutes and Regulations
Principal law
United StatesAdministrative Procedure Act (APA)United StatesNational Environmental Policy Act (NEPA)United StatesNational Wildlife Refuge System Improvement Act of 1997
At issue
Challenge to federal agency actions that would facilitate development of a high-voltage transmission line from Dubuque County, Iowa, to Middleton, Wisconsin, passing through the Upper Mississippi River National Wildlife and Fish Refuge.

Documents

Filing Date
Document
Type
09/24/2025
Federal defendants' and intervenor-defendants' motions for summary judgment granted.
The federal district court for the Western District of Wisconsin granted summary judgment to federal defendants and intervenor-defendant utilities in a challenge to a land exchange that granted the utilities fee ownership of land within the Upper Mississippi River National Wildlife and Fish Refuge to facilitate completion of a 101-mile high-voltage transmission line. The court concluded that the action was not moot even though the transmission line project had been completed and placed in service in September 2024, but on the merits the court rejected arguments that the exchange violated the National Wildlife Refuge System Improvement Act of 1997 and the National Environmental Policy Act (NEPA). The court found that the U.S. Fish and Wildlife Service’s (FWS’s) analysis of the land exchange—“the only reviewable federal action”—complied with NEPA because FWS considered possible environmental impacts, including climate consequences, and a reasonable range of alternatives. With respect to climate impacts, the court noted that a supplemental environmental assessment had found that the land exchange and related route modifications would not change the minor, long-term increase in greenhouse gas emissions over the previously approved transmission line project and that “very minor” climate benefits were expected from carbon sequestration resulting from management for resource conservation purposes of the new property incorporated into the refuge. The court also found that the defendants complied with NEPA’s public participation requirements.
Decision
03/25/2024
Land transfer enjoined to allow production and review of administrative record.
The court preliminarily enjoined the federal defendants and developers from taking action to close an agreement to exchange 19.84 acres of land within the refuge for 35.69 acres of land held by two of the developers. The injunction also barred commencement of construction on the line through the refuge until the court had an opportunity to consider the administrative record underlying the agencies’ February 2024 decisions. The court stated that “[t]here are a number of problems with the [developers] being allowed to proceed. Most fundamentally, federal defendants and [the developers] have orchestrated the events here to preclude judicial review of the final determination until after substantial damage has already been done to what until now was the Refuge. Whatever the merits of plaintiffs’ challenge to the federal defendants’ decision to proceed with the land exchange under the relevant statutes, some meaningful review by this court is necessary to determine ‘whether that decision is supported by substantial evidence.’”
Decision
03/20/2024
Opposition to preliminary injunction motion filed by owners of a portion of the transmission line project.
Opposition
03/13/2024
Brief filed in support of plaintiffs' motion for preliminary injunction.
Motion
03/06/2024
Complaint filed.
Three conservation groups filed a lawsuit in the federal district court for the Western District of Wisconsin challenging federal agency actions that facilitate development of a high-voltage transmission line from Dubuque County, Iowa, to Middleton, Wisconsin, passing through the Upper Mississippi River National Wildlife and Fish Refuge. The plaintiffs asserted violations of NEPA, the Administrative Procedure Act, and the National Wildlife Refuge System Improvement Act. The plaintiffs <a href="https://climatecasechart.com/case/national-wildlife-refuge-association-v-rural-utilities-service/">previously challenged</a> approvals for the project. The district court granted a preliminary injunction, but the Seventh Circuit Court of Appeals concluded that the case did not present a reviewable final agency decision. In the new lawsuit, the plaintiffs alleged that the agencies had made final agency decisions in February 2024 when they issued a final EIS and record of decision and supplemental environmental assessment. The complaint alleged that these documents violated NEPA, including by failing to take a hard look at climate change impacts even though the federal defendants and the transmission line developers acknowledged the line would carry electricity from fossil fuel power plants.
Complaint

Summary

Challenge to federal agency actions that would facilitate development of a high-voltage transmission line from Dubuque County, Iowa, to Middleton, Wisconsin, passing through the Upper Mississippi River National Wildlife and Fish Refuge.