The question of implementation arose with respect to Ukraine’s 2010 annual inventory submission. Consequently, it was found that the Ukrainian national system did not operate fully in accordance with the general and specific functions as set out in the guidelines for national systems. In particular, the institutional, legal and procedural arrangements failed in estimating emissions and sinks covered by the Protocol, and for reporting and archiving this information in accordance with the methods described in the revised 1996 IPCC guidelines. Further, the national system was unable to ensure consistent land representation in accordance with the IPCC good practice guidance and unable to account for all carbon stock changes.
On 12 October 2011, the enforcement branch determined that Ukraine was not in compliance with the guidelines for national systems and consequently not eligible to participate in the transfer and sale of emission credits. In December 2011 and February 2012, Ukraine submitted its plan of implementation and updated reports respectively. On 9 March 2012, the branch decided that there no longer continued to be a question of implementation with respect to Ukraine's eligibility and reinstated Ukraine’s eligibility eligible to participate in the mechanisms under articles 6, 12 and 17 of the Protocol.
- Climate Litigation Database
- /
- Search
- /
- Non-compliance Procedure of Ukraine under the Kyoto Protocol
Non-compliance Procedure of Ukraine under the Kyoto Protocol
Geography
International
Year
2011
Document Type
Litigation
About this case
Filing year
2011
Status
Decided
Geography
International
Court/admin entity
United Nations → United Nations Framework Convention on Climate Change
Case category
Suits against governments (Global) → GHG emissions reduction and trading (Global) → Kyoto Protocol (Global)
Principal law
International Law → Kyoto Protocol Compliance TribunalsInternational Law → UNFCCC → Kyoto Protocol
Topics
, ,
Documents
Each case in our database can contain one or more documents.
Filing Date
Document
Type
Topics
03/09/2012
Decision regarding reinstatement of eligibility
Other
Other land use mitigationGreenhouse gasFinance flow
12/08/2011
Compliance Implementation Plan
Other
Greenhouse gasOther land use mitigationFinance flowFossil fuel+ 3 more
10/12/2011
Final Decision of the Enforcement Branch of the Compliance Committee
Other
Other land use mitigationGreenhouse gasDirect investmentJust transition+ 3 more
06/11/2011
Report of the individual review of the annual submission of Ukraine submitted in 2010
Other
Greenhouse gasCarbon dioxideOther land use mitigationFossil fuel+ 26 more
Summary
Topics mentioned most in this case
See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.
Group
Topics
Policy instrument
Risk
Just transition
Renewable energy
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance