Red Lake Band of Chippewa Indians v. Minnesota Public Utilities Commission (In re Enbridge Energy, LP)
Geography
Year
2020
Document Type
Litigation
Part of
About this case
Filing year
2020
Status
Brief filed in support of motion for stay pending appeal of relators Red Lake Band of Chippewa Indians and White Earth Band of Ojibwe.
Geography
Docket number
A20-1072
Court/admin entity
United States → State Courts → Minnesota Court of Appeals (Minn. Ct. App.)
Case category
State Law Claims (US) → Environmentalist Lawsuits (US)State Law Claims (US) → State Impact Assessment Laws (US)
Principal law
United States → Minnesota Environmental Policy Act
At issue
Challenge to Minnesota Public Utilities Commission authorization of Line 3 pipeline project.
Topics
, ,
Documents
Filing Date
Document
Type
Topics
Beta
12/29/2020
Brief filed in support of motion for stay pending appeal of relators Red Lake Band of Chippewa Indians and White Earth Band of Ojibwe.
Brief
12/29/2020
Motion for stay pending appeal filed by relators Red Lake Band of Chippewa Indians and White Earth Band of Ojibwe.
Motion
08/18/2020
Petition for writ of certiorari filed.
The Red Lake Band of Chippewa Indians, the White Earth Band of Ojibwe, Honor the Earth, and Sierra Club filed petition in the Minnesota Court of Appeals challenging the decisions by the Minnesota Public Utilities Commission authorizing the Line 3 project. Issues to be raised in this proceeding include the petitioners’ contention that the PUC “decided to entirely disregard most of the climate change impacts of the Project,” contrary to its obligations to consider effects on Minnesota’s natural and socioeconomic environment and to consider climate change’s economic and environmental costs on people within Minnesota, “including the Anishinaabe peoples who claim a right to continue to live on their lands in accordance with their beliefs and culture, which is their human and legal right to do.”
Petition For Writ Of Certiorari
08/18/2020
Statement of the case filed by petitioners.
Statement
Summary
Challenge to Minnesota Public Utilities Commission authorization of Line 3 pipeline project.
Topics mentioned most in this case Beta
See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more
Group
Topics
Policy instrument
Risk
Impacted group
Just transition
Fossil fuel
Greenhouse gas
Economic sector
Finance