San Antonio Bay Estuarine Waterkeeper v. Connor

About this case

Filing year
2022
Status
Joint status report and stipulation of dismissal filed.
Docket number
1:22-cv-01470
Court/admin entity
United StatesUnited States Federal CourtsUnited States District Court for the District of Columbia (D.D.C.)
Case category
Federal Statutory Claims (US)NEPA (US)
Principal law
United StatesAdministrative Procedure Act (APA)United StatesClean Water Act (CWA)United StatesNational Environmental Policy Act (NEPA)
At issue
Challenge to U.S. Army Corps of Engineers authorizations for a federal channel deepening and expansion project in the Matagorda Ship Channel near Port Lavaca, Texas.
Topics
, ,

Documents

Filing Date
Document
Type
Topics 
Beta
03/08/2023
Joint status report and stipulation of dismissal filed.
Stipulation
12/13/2022
Defendants filed notice of withdrawal of record of decision.
On December 13, 2022, the U.S. Army Corps of Engineers notified the federal district court for the District of Columbia of its withdrawal of the record of decision for the Matagorda Ship Channel Improvement Project Feasibility Report and Environmental Impact Statement. Five environmental groups had challenged the Corps’ authorizations for the channel deepening and expansion project that was the subject of the record of decision, including for failing to disclose the climate impacts of a major new crude export site facilitated by the project. The Corps announced on December 5 that it would prepare a supplemental EIS due to a discrepancy between the quantity of dredged material evaluated in a 2019 EIS for the project and the quantity calculated more recently during the pre-construction, engineering, and design phase.
Notice
05/25/2022
Complaint filed.
Five environmental groups filed a lawsuit in the federal district court for the District of Columbia alleging that U.S. Army Corps of Engineers authorizations for a federal channel deepening and expansion project in the Matagorda Ship Channel near Port Lavaca, Texas, violated NEPA and the Clean Water Act. The allegations included that the Corps was required to prepare a supplemental environmental impact statement (EIS) to consider, among other things, the potential greenhouse gas emissions and national climate policy implications of a major new crude export site that was announced after issuance of the final EIS and which would be facilitated by the channel expansion project. The plaintiffs also alleged that the final EIS’s cost-benefit analysis did not consider certain categories of costs, including climate impacts.
Complaint

Summary

Challenge to U.S. Army Corps of Engineers authorizations for a federal channel deepening and expansion project in the Matagorda Ship Channel near Port Lavaca, Texas.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Policy instrument
Risk
Impacted group
Just transition
Renewable energy
Fossil fuel
Greenhouse gas
Economic sector
Finance