Sierra Club v. Federal Energy Regulatory Commission
Geography
Year
2022
Document Type
Litigation
Part of
About this case
Filing year
2022
Status
Petition for review denied.
Geography
Docket number
22-1233
Court/admin entity
United States → United States Federal Courts → United States Court of Appeals for the District of Columbia (D.C. Cir.)
Case category
Federal Statutory Claims (US) → NEPA (US)Federal Statutory Claims (US) → Other Statutes and Regulations (US)
Principal law
United States → National Environmental Policy Act (NEPA)United States → Natural Gas Act
At issue
Challenge to the Federal Energy Regulatory Commission's grant of a request for an extension of time for construction and placement into service of a natural gas pipeline project in New York.
Topics
, ,
Documents
Filing Date
Document
Type
Topics
Beta
03/29/2024
Petition for review denied.
The D.C. Circuit Court of Appeals denied petitions for review challenging the Federal Energy Regulatory Commission’s extensions of construction deadlines for the 99-mile Northern Access Pipeline in Pennsylvania and New York and for improvements to an <a href="https://climatecasechart.com/case/sierra-club-v-federal-energy-regulatory-commission-6/">existing liquefied natural gas terminal</a> on Corpus Christi Bay in Texas and a related pipeline. The D.C. Circuit found that FERC’s decisions were reasonable and adequately supported by record evidence. Regarding the Northern Access Pipeline, the D.C. Circuit rejected the petitioner’s argument that FERC acted arbitrarily and capriciously by failing to consider the impacts of New York’s 2019 climate law on the market need for the project, as well as the related argument that the 2019 law’s effects necessitated preparation of a supplemental environmental impact statement.
Decision
09/06/2022
Petition for review filed.
Sierra Club filed a petition for review in the D.C. Circuit Court of Appeals challenging the Federal Energy Regulatory Commission's (FERC’s) grant of a request for a 35-month extension of time for construction and placement into service of the Northern Access 2016 Project, which would involve construction of approximately 99 miles of natural gas pipeline in New York, a new compressor station, additional compression at an existing compressor station, and various appurtenant facilities. Arguments before FERC included that greater understanding of the impacts of climate change and the significance of greenhouse gas emissions constituted new information requiring updated environmental analysis.
Petition
Summary
Challenge to the Federal Energy Regulatory Commission's grant of a request for an extension of time for construction and placement into service of a natural gas pipeline project in New York.
Topics mentioned most in this case Beta
See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more
Group
Topics
Policy instrument
Fossil fuel
Economic sector
Finance