Skip to content
The Climate Litigation Database

Sierra Club v. U.S. Department of Energy

About this case

Filing year
2025
Status
Petition for review filed.
Docket number
25-1160
Court/admin entity
United StatesUnited States Federal CourtsUnited States Court of Appeals for the District of Columbia (D.C. Cir.)
Case category
Federal Statutory Claims (US)Other Statutes and Regulations (US)
Principal law
United StatesFederal Power Act
At issue
Challenges to Secretary of Energy’s order determining that an emergency existed in the Midwest due to shortages of electric energy and electric generation facilities and ordering Campbell coal-fired power plant to remain available to operate.
Topics
, ,

Documents

Filing Date
Document
Type
Topics 
Beta

Summary

Challenges to Secretary of Energy’s order determining that an emergency existed in the Midwest due to shortages of electric energy and electric generation facilities and ordering Campbell coal-fired power plant to remain available to operate.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Target
Policy instrument
Risk
Impacted group
Renewable energy
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience