Skip to content
The Climate Litigation Database

Wilderness Society Ltd v National Offshore Petroleum Safety and Environmental Management Authority

Geography
🇦🇺 Australia
Year
2025
Document Type
Litigation

About this case

Filing year
2025
Status
Decided
Geography
🇦🇺 Australia
Court/admin entity
Australia → Federal Court of Australia
Case category
Suits against governments (Global) → Environmental assessment and permitting (Global)Suits against governments (Global) → Protecting biodiversity and ecosystems (Global)
Principal law
Australia → Offshore Petroleum and Greenhouse Gas Storage Act 2006 (Cth)Australia → Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2023 (Cth)
Topics
, ,  

Documents

Each case in our database can contain one or more documents.

Filing Date
Document
Type
Topics
08/07/2026
Decision
Fossil fuelOilConstruction sectorFinance flow+ 18 more

Summary

In August 2025, the Wilderness Society Ltd (TWS), an Australian environmental NGO, sought an order setting aside a decision by the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) (the first respondent) to accept the Reindeer Wellhead Platform and Gas Supply Pipeline Operations and Cessation of Production Environment Plan (Reindeer EP). The Reindeer EP was sought by Santos WA Northwest Pty Ltd (Santos) (the second respondent to the proceedings) — a titleholder of a petroleum production licence and a pipeline licence over areas in the Barrow Sub-basin on the North West Shelf, off the coast of Western Australia — on April 24, 2025.

NOPSEMA accepted the Reindeer EP under regulation 33 of the Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2023 (Cth) (the Regulations), which require NOPSEMA to accept an environmental plan if it is reasonably satisfied certain criteria. However,  NOPSEMA must not have accepted the Reindeer EP unless Santos is compliant with section 571(2) of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 (Cth) (the Act).

TWS alleged that NOPSEMA “misconstrued s 571(2) of the [Act] as not requiring a financial assurance to deal with decommissioning costs, expenses and liabilities and therefore could not have been reasonably satisfied that [Santos] is compliant with s 571(2) of the [Act] in relation to the petroleum activity,” as required by the Regulations.

According to records, the delegate of NOPSEMA approved the Reindeer EP on the basis that they were “reasonably satisfied that the titleholder was compliant with s 571(2), and the financial assurance declaration and confirmation forms were acceptable.” TWS wrote to NOPSEMA to inquire as to whether it had received financial assurance to meet decommissioning costs. An employee of NOPSEMA replied stating that “[t]he assessment does not… extend to the evaluation of financial assurance provisions intended to address decommissioning liabilities.”

In their submissions, TWS argued that NOPSEMA erred, and that the financial assurance obligation is broad, imposing a requirement to maintain financial assurance relating to obligations imposed by the Act, which properly encompasses decommissioning. The respondents contended that the financial assurance obligation focuses on the particular activity which is the subject of the environmental plan in question.  

On August 7, 2026, Justice Abraham of the Federal Court of Australia agreed that the requirements imposed in relation to submission and assessment of environmental plans are focused on the particular activity the titleholder proposes in the plan. Justice Abraham further found that NOPSEMA had in fact determined that decommissioning was not part of the scope of the Reindeer EP, which would be covered under a subsequent environment plan, and therefore found no error in NOPSEMA’s satisfaction that the environment plan complied with the requirements. Justice Abraham also concluded that the applicant’s reliance on the email from the NOPSEMA employee was misplaced in circumstances where it did not come from the delegate themselves and did not form a part of the reasons for NOPSEMA’s decision.

The application was dismissed with costs.

 Topics mentioned most in this case

See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.

Group
Topics
Policy instrument
Risk
Impacted group
Just transition
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance