Skip to content
The Climate Litigation Database
Collection

Delaware Riverkeeper Network v. U.S. Army Corps of Engineers

Delaware Riverkeeper Network v. U.S. Army Corps of Engineers 

17-1506United States Third Circuit (3d Cir.)1 entry
Filing Date
Type
Action Taken
Document
Summary
08/23/2017
Decision
Petition for review denied.
The Third Circuit Court of Appeals upheld a Clean Water Act permit issued for an interstate gas pipeline project by the U.S. Army Corps of Engineers. The court found that the Corps had considered a "compression alternative" that would have increased the amount of gas transported through existing pipelines and had rejected it for reasons supported by the record. The compression alternative would have required construction of one or more permanent fixtures, "causing permanent deforestation as well as light, air, sound, and greenhouse gas pollution. The Third Circuit stated: "In making a policy choice between those environmental tradeoffs, the agency’s discretion was at its apex. We will therefore deny the petition for review."