Skip to content
The Climate Litigation Database

Delaware Riverkeeper Network v. U.S. Army Corps of Engineers

Geography
Year
2017
Document Type
Litigation
Part of

About this case

Filing year
2017
Status
Petition for review denied.
Geography
Docket number
17-1506
Court/admin entity
United States → United States Federal Courts → United States Court of Appeals for the Third Circuit (3d Cir.)
Case category
Federal Statutory Claims (US) → Clean Water Act (US)Federal Statutory Claims (US) → NEPA (US)
Principal law
United States → Clean Water Act (CWA)United States → National Environmental Policy Act (NEPA)United States → Natural Gas Act
At issue
Challenge to Clean Water Act permits for natural gas interstate pipeline project.
Topics
, ,  

Documents

Each case in our database can contain one or more documents.

Filing Date
Document
Type
Topics
08/23/2017
Petition for review denied.
The Third Circuit Court of Appeals upheld a Clean Water Act permit issued for an interstate gas pipeline project by the U.S. Army Corps of Engineers. The court found that the Corps had considered a "compression alternative" that would have increased the amount of gas transported through existing pipelines and had rejected it for reasons supported by the record. The compression alternative would have required construction of one or more permanent fixtures, "causing permanent deforestation as well as light, air, sound, and greenhouse gas pollution. The Third Circuit stated: "In making a policy choice between those environmental tradeoffs, the agency’s discretion was at its apex. We will therefore deny the petition for review."
Decision
Fossil fuelGasConstruction sectorTransportation and logistics sector+ 8 more

Summary

Challenge to Clean Water Act permits for natural gas interstate pipeline project.

 Topics mentioned most in this case

See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.

Group
Topics
Risk
Fossil fuel
Greenhouse gas
Economic sector
Finance