Skip to content
The Climate Litigation Database
Collection

Save the Colorado v. Semonite

Save the Colorado v. Spellmon 

21-1155United States Federal Courts, United States Tenth Circuit (10th Cir.)6 entries
Filing Date
Type
Action Taken
Document
Summary
09/30/2022
Decision
Dismissal of case reversed.
The Tenth Circuit Court of Appeals ruled that a federal district court erred when it concluded that the Federal Power Act vested the courts of appeals with exclusive jurisdiction over a challenge to a U.S. Army Corps of Engineers permit that was required for modification of a dam project licensed by the Federal Energy Regulatory Commission. The environmental groups challenging the Corps permit contended, among other things, that the Corps violated the National Environmental Policy Act by failing to fully consider the impacts of climate change. The Tenth Circuit reversed the district court’s dismissal of the case and remanded for further proceedings.
01/13/2022
Reply
Reply brief filed by appellants.
11/15/2021
Motion
Board of County Commissioners of Boulder County filed unopposed motion to withdraw amicus brief in support of petitioners-appellants.
11/10/2021
Brief
Answering brief filed by federal appellees.

Save the Colorado v. Semonite 

1:18-cv-03258United States District of Colorado (D. Colo.), United States Federal Courts12 entries
Filing Date
Type
Action Taken
Document
Summary
04/06/2025
Decision
Motion for stay pending appeal denied and 14-day temporary stay granted.
On April 6, 2025, the court denied the Denver Water’s emergency motion to stay pending appeal both the April 3 preliminary injunction order and the underlying October 2024 order but granted a 14-day temporary stay of the preliminary injunction to allow Denver Water an opportunity to seek a stay from the Tenth Circuit.
04/03/2025
Decision
Permit vacated and construction enjoined pending hearing.
On April 3, 2025, the federal district court for the District of Colorado concluded that remand with vacatur was the appropriate remedy for the U.S. Army Corps of Engineers’ violations of the Clean Water Act, the National Environmental Policy Act, and the Administrative Procedure Act when it issued a permit allowing the City and County of Denver’s Board of Water Commissioners (Denver Water) to expand the Gross Dam and Reservoir. The court found that an “amalgamation of … serious defects,” including a failure to quantify climate change’s effects on precipitation, supported vacatur as a remedy. The court also rejected the respondents’ and intervenor’s arguments that vacatur would not impact further construction because construction could proceed under a Federal Energy Regulatory Commission license and that remand with vacatur would cause environmental harm because the Corps permit gave it authority to enforce protective conditions. The court temporarily enjoined construction on the dam pending a hearing on a permanent construction injunction tailored to the amount of additional construction necessary to make the existing dam safe. The court permanently enjoined enlargement of the Gross Reservoir.
10/16/2024
Decision
Court ruled that Corps violated NEPA and the Clean Water Act.
The federal district court for the District of Colorado ruled that the U.S. Army Corps of Engineers violated the Clean Water Act and the National Environmental Policy Act (NEPA) when the Corps issued a dredge-and-fill permit to the Denver municipal water entity for expansion of the Gross Dam and Reservoir. The court first addressed jurisdictional issues, finding that the petitioners had standing and that the case was not moot. Regarding the Clean Water Act, the court found that the administrative record did not disprove that alternatives that would not have required disturbance of wetlands were both practicable and available. The court also found that the Corps did not demonstrate that the project was the “least environmentally damaging practicable alternative” (LEDPA), including because the Corps ignored foreseeable effects of climate change on precipitation. The court wrote that “despite acknowledging that future climate conditions might neuter the Gross Dam’s value as a water storage solution, the Corps expressly declined to attempt to quantify the impacts of climate change—or even provide an educated guess, for purposes of discussion”—which the court said “proves fatal” to the LEDPA finding because “if the Gross Reservoir has no extra water to impound, or that water is lost to the sun or flora, the Proposed Action cannot possibly be practicable in a logistical sense.” Under NEPA, the court found that the Corp improperly merged “two conceptually distinct project purposes” and also failed to take a hard look at relevant issues, including climate change. The court said the Corps’ “refusal to provide even an estimate on future hydrology is indefensible, an abject violation of NEPA.” The court was not persuaded by the respondents’ contention that uncertainty justified the lack of consideration to climate impacts on precipitation. The court said that even if NEPA did not require quantification of such impacts, the Corps was “at least” obligated to “consider whether the practicability of a given alternative would change if the negative consequences identified in its qualitative analysis came to pass.” The court rejected a claim that the U.S. Fish and Wildlife Service violated the Endangered Species Act and deferred a final ruling on a specific remedy until after submission of further briefing.
03/31/2021
Decision
Motions to dismiss granted.
The federal district court for the District of Colorado agreed with federal respondents that the Federal Power Act (FPA) required that petitioners’ challenges to U.S. Army Corps of Engineers and U.S. Fish and Wildlife Service (FWS) actions authorizing a dam project in Colorado be brought in a federal court of appeal. The district court noted that the FPA vests federal courts of appeal with exclusive jurisdiction to review not only the licensing orders of the Federal Energy Regulatory Commission (FERC) but also “all issues inhering in the controversy” related to a FERC order. In this case, the court found that the Corps, FERC, and FWS decisions were “inextricably intertwined.” The court therefore dismissed the case—which alleged, among other things, that the federal agencies failed to take into account climate change impacts and future climate change models—for lack of jurisdiction.

Save the Colorado v. Graham 

25-1137United States Federal Courts, United States Tenth Circuit (10th Cir.)2 entries
Filing Date
Type
Action Taken
Document
Summary
04/21/2025
Reply
Reply filed in support of emergency motion for stay pending appeal.
04/17/2025
Opposition
Opposition filed by petitioners-appellees to Denver Water's motion for a stay pending appeal.