Skip to content
The Climate Litigation Database
Litigation

Citizens for Clean Energy v. U.S. Department of Interior

About this case

Documents

Filing Date
Type
Action Taken
Document
Summary
08/12/2022
Decision
Plaintiffs' motions for summary judgment granted in part and denied as moot in part and defendants' and intervenors' motions for summary judgment and to dismiss denied.
The federal district court for the District of Montana vacated and remanded the final environmental assessment and finding of no significant impact that the U.S. Bureau of Land Management (BLM) prepared for former Secretary of the Interior Ryan Zinke’s 2017 order that terminated a NEPA review of the federal coal leasing program ordered by former Secretary of the Interior Sally Jewell and directed BLM to resume issuing coal leases. The court previously ruled that Zinke’s order constituted major federal action requiring NEPA review. At issue in this case was whether BLM’s subsequent review satisfied National Environmental Policy Act (NEPA) requirements. As an initial matter, the court held that Secretary of the Interior Deb Haaland’s order revoking Secretary Zinke’s order did not moot the claims because the coal leasing moratorium put in place by former Secretary Jewell remained revoked. On the merits, the court found that BLM’s environmental assessment did not satisfy NEPA and Administrative Procedure Act requirements because its limited analysis of four leases deemed traceable to the Zinke order failed to consider all direct, indirect, and cumulative impacts of restarting the coal leasing program. The court said BLM should have used a status quo of a moratorium on coal leasing as its baseline alternative and should not have presumed that the moratorium was limited to the three-year period anticipated for completion of the programmatic environmental impact statement for the coal leasing program. The court further found that BLM “arbitrarily curtailed” even its assessment of the four leases’ impacts. The court reinstated the moratorium pending completion of sufficient NEPA review.
03/22/2022
Reply
Reply filed by federal defendants in support of cross-motion for summary judgment.
02/24/2022
Brief
State plaintiffs filed brief in opposition to defendants' cross-motions for summary judgment and reply in support of motion for summary judgment.
02/24/2022
Reply
Response and reply brief filed in support of plaintiffs' motion for summary judgment on supplemental complaint.
02/17/2022
Reply
Reply filed by intervenor-defendant National Mining Association in support of motion to dismiss for mootness.
02/03/2022
Opposition
Joint brief filed by plaintiffs in opposition to National Mining Association's motion to dismiss.
01/27/2022
Motion For Summary Judgment
Memorandum of points and authorities filed by intervenor-defendant National Mining Association in support of cross-motion for summary judgment and opposition to plaintiffs' motion for summary judgment.
01/27/2022
Motion For Summary Judgment
Joint memorandum filed by intervenor-defendants Wyoming and Montana in support of cross motion for summary judgment and in response to plaintiffs' motion for summary judgment.
01/20/2022
Response
Brief filed by federal defendants in response to National Mining Association motion to dismiss.
01/20/2022
Brief
Brief filed by intervenor-defendants Wyoming and Montana in support of National Mining Association motion to dismiss.
01/13/2022
Motion For Summary Judgment
Memorandum filed by federal defendants in support of cross-motion for summary judgment and opposing plaintiffs' motion for summary judgment.
01/05/2022
Decision
Order issued regarding briefing schedule.
12/10/2021
Status Report
Joint status report filed.
07/13/2021
Decision
Joint motion for stay granted.
07/12/2021
Motion
Joint motion for stay of proceedings filed.
07/06/2021
Motion
Memorandum of points and authorities filed by intervenor-defendant National Mining Association in support of motion to dismiss for mootness.
06/03/2021
Decision
Federal defendants' motion for stay denied.
The federal district court for the District of Montana denied federal defendants’ request for a 90-day stay in proceedings challenging the Trump administration’s lifting of the Obama administration’s moratorium on federal coal leasing. Briefing is currently underway on summary judgment motions regarding the adequacy of the U.S. Bureau of Land Management’s (BLM’s) environmental assessment (EA) and finding of no significant impact (FONSI) for the lifting of the moratorium. BLM issued the EA and FONSI in response to the court’s 2019 decision finding that the lifting of the moratorium was a “major federal action” requiring review under the National Environmental Policy Act. In April 2021, Secretary of the Interior Deb Haaland issued Secretarial Order 3398, which revoked former Secretary Ryan Zinke’s order that lifted the moratorium. Secretary Haaland’s order directed agencies to prepare a report with a plan for reversing, amending, or updating the policies implementing the Zinke order. The court found, however, that there was a “fair possibility” that previous and ongoing implementation of the Zinke order’s policies would cause damage to the plaintiffs’ interests in air quality, water quality, wildlife habitat, cultural sites, and mitigation of climate change impacts. The court further found that the federal defendants failed to establish that they would suffer hardship if the case proceeded and that “the orderly course of justice further weighs in favor of the Court maintaining the current schedule” since it “remains doubtful that Federal Defendants can complete their agency review and related policy change within a reasonable time.”
06/01/2021
Opposition
Joint brief filed by environmental group plaintiffs in opposition to federal defendants' motion to stay.
05/18/2021
Motion For Summary Judgment
Brief filed in support of plaintiffs' motion for summary judgment on the supplemental complaint.
05/18/2021
Motion For Summary Judgment
Brief filed by state plaintiffs in support of motion for summary judgment.
05/17/2021
Motion
Motion for stay filed by defendants.
07/23/2020
Decision
Plaintiffs' joint motion for leave to supplement their complaints granted.
The federal district court for the District of Montana allowed plaintiffs to supplement their complaints in lawsuits challenging the U.S. Department of the Interior’s failure to comply with the National Environmental Policy Act (NEPA) when it lifted the moratorium on the federal coal leasing program. The plaintiffs sought to challenge the environmental assessment (EA) prepared by the defendants after the court ruled that lifting the moratorium was an action subject to NEPA. The plaintiffs alleged several flaws in the EA, including ignoring cumulative impacts and arbitrarily refusing to use the social cost of carbon or another metric to assess greenhouse gas impacts. The plaintiffs also contended that the absence of consideration in the EA and finding of no significant impact of the long-term public benefits of addressing climate change and other impacts violated the Mineral Leasing Act.
07/20/2020
Brief
Brief filed in support of plaintiffs' joint motion for leave to supplement their complaints.
07/20/2020
Motion
Joint motion filed by plaintiffs for leave to supplement their complaints.
07/20/2020
Complaint
Proposed first supplemental complaint filed by environmental groups.
07/20/2020
Complaint
Proposed first supplemental complaint filed by states.
05/22/2020
Decision
Plaintiffs' requested relief denied and case closed.
The federal district court for the District of Montana found that the U.S. Department of the Interior, the Secretary of the Interior, and the U.S. Bureau of Land Management (BLM) had complied with the court’s previous order requiring them to initiate the NEPA process in connection with the Trump administration’s lifting of the moratorium on the federal coal leasing program. Secretary of the Interior Sally Jewell instituted the moratorium in January 2016 and directed BLM to prepare a programmatic environmental impact statement for the federal coal program that addressed climate change, among other issues. After the court’s previous order, BLM in February 2020 issued a final environmental assessment (EA) and finding of no significant impact (FONSI); the court noted that the EA’s analysis was based on analysis of the impacts of resuming coal lease processing 24 months earlier and that the FONSI “relies heavily on the fact that the [moratorium] disrupted a 40-year framework for coal leasing, and the finite nature of the [moratorium], together with the NEPA review of individual leases limited the effects” of lifting the moratorium. The court rejected the plaintiffs’ contention that the final EA and FONSI did not remedy the NEPA violations identified by the court. Although the court declined to engage in a substantive review of the EA and FONSI “without a new complaint and administrative record to review,” it said the plaintiffs “remain free to challenge the sufficiency of the NEPA analysis.”
05/05/2020
Reply
Reply brief on remedy filed by plaintiffs.
04/21/2020
Response
Response filed by federal defendants to plaintiffs' substitute brief on remedy.
04/21/2020
Brief
Joint substitute brief on remedy filed by intervenor-defendants State of Wyoming, State of Montana, and National Mining Association.
03/18/2020
Request
Request for a status conference filed by federal defendants.
03/10/2020
Brief
Substitute brief on remedy filed by plaintiffs.
02/27/2020
Notice
Defendant filed notice of publication of finding of no significant impact and environmental assessment.
Federal defendants notified the federal district court for the District of Montana that they had posted a <a href="https://eplanning.blm.gov/epl-front-office/projects/nepa/122429/20013723/250018743/Lifting_Coal_Pause_FONSI.FINAL_Signed.pdf">finding of no significant impact</a> (FONSI) and final <a href="https://eplanning.blm.gov/epl-front-office/projects/nepa/122429/20013717/250018737/Lifting_the_Pause_for_Coal_Final_EA.pdf">environmental assessment</a> (EA) on the U.S. Bureau of Land Management website to comply with the court’s April 2019 ruling that the lifting of the Obama administration’s moratorium on coal leasing was a “major federal action” triggering obligations under the National Environmental Policy Act (NEPA). The FONSI stated that “[i]n the Department [of the Interior]’s view,” the order lifting the moratorium “does not have environmental effect because it does not, in itself, authorize sale or issuance of any new coal leases.” The FONSI indicated that the Department of the Interior believed that the order did not alter substantive law but merely altered a choice the Obama administration made that the Department believed was inconsistent with existing law. The FONSI said the Final EA “documented the effects and consequences of lifting the [moratorium] and resuming application processing sooner than anticipated.” Because of the “temporary nature” of the Obama administration moratorium, the FONSI concluded that the effects of lifting the moratorium were “limited to the timing of lease issuances” and that resumption of leasing practices, including compliance with NEPA, therefore “created no significant, unstudied impacts.”
07/31/2019
Decision
Order issued postponing ruling on remedies.
The federal district court for the District of Montana postponed its remedies ruling in the case challenging Secretary of the Interior Ryan Zinke’s lifting of the Obama administration’s moratorium on federal coal leasing. In April 2019, the court ruled that the lifting of the moratorium was subject to the National Environmental Policy Act (NEPA), and in May, the federal defendants issued a 35-page draft environmental assessment (EA). Although the plaintiffs argued that the appropriate remedy for the defendants’ failure to comply with NEPA was vacatur and contended that the draft EA did not overcome the deficiencies, the court concluded that it was appropriate to postpone a ruling on remedies to allow the federal defendants to complete their environmental review. The defendants told the court that they anticipated they would reach a determination on whether an environmental impact statement was required by August 5, 2019.
07/22/2019
Brief
Remedy brief filed by federal defendants.
07/22/2019
Brief
Joint brief on remedy filed by intervenor-defendants Wyoming, Montana, and National Mining Association.
07/22/2019
Brief
Brief on remedy filed by plaintiffs.
06/18/2019
Decision
Federal defendants' motion for enlargement of time for remedy briefing.
The federal district court for the District of Montana granted the federal government more time to submit briefing on the appropriate remedies for the government’s failure to comply with the National Environmental Policy Act (NEPA) when Secretary of the Interior Ryan Zinke lifted the Obama administration’s moratorium on the federal coal leasing program. The federal government notified the court on May 22, 2019 that it had published a <a href=https://eplanning.blm.gov/epl-front-office/projects/nepa/122429/173355/210563/Lifting_BLM_Coal_Leasing_Pause_EA.pdf>draft environmental assessment</a> (EA) for the coal program in partial compliance with the court’s April 2019 order that found violations of NEPA and the Administrative Procedure Act. The plaintiffs countered that remedies briefing was still necessary despite publication of the draft EA. The court directed that the parties submit remedy briefs by the earlier of (1) 14 days after the defendants determine whether to issue a finding of no significant impact or to prepare an environmental impact statement or (2) July 22, 2019. The public comment period on the draft EA ended on June 10.
05/30/2019
Response
Response filed by plaintiffs to federal defendants' notice of partial compliance.
The Northern Cheyenne Tribe and conservation groups subsequently filed a response indicating that they did not view publication of the draft EA as “partial compliance” with the court’s April 2019 order finding that the lifting of the moratorium required compliance with NEPA. The Tribe and conservation groups said they would therefore submit a brief regarding appropriate remedies for the federal defendants’ NEPA violations.
05/22/2019
Notice
Federal defendants filed notice of partial compliance with April 19, 2019 order and of the availability of an environmental assessment.
The federal defendants filed a notice of partial compliance with the federal district court for the District of Montana to inform the court that it had published a draft environmental assessment (EA) that considers the environmental impacts of former Secretary of the Interior Ryan Zinke’s lifting of the moratorium on the federal coal program.
04/19/2019
Decision
Plaintiffs' and defendants' motions and cross-motions for summary judgment granted in part and denied in part.
The federal district court for the District of Montana ruled that the Trump administration’s lifting of a moratorium on coal leasing triggered the need to comply with the National Environmental Policy Act (NEPA). Secretary of the Interior Sally Jewell issued an order in January 2016 directing the U.S. Bureau of Land Management (BLM) to prepare a programmatic environmental impact statement (PEIS) for the federal coal leasing program. The order also imposed a moratorium on coal leasing until the PEIS was completed. In March 2017, Secretary of the Interior Ryan Zinke issued an order determining that a PEIS was not necessary and lifting the moratorium. The district court found that the Zinke order met the requirements both for “major federal action” triggering obligations under NEPA and also for reviewable final agency action under the Administrative Procedure Act. The court also determined, as threshold matters, that the state and organizational plaintiffs had standing and that their claims were ripe. Although the court concluded that it could not at this point compel the defendants to prepare a PEIS, it ordered the defendants to take the initial step under NEPA of determining the extent of environmental analysis that was necessary. The court also directed the parties to attempt to reach an agreement on potential remedies within 30 days or, alternatively, if they could not reach agreement, to submit briefing on the Monsanto factors for permanent injunctive relief.
12/03/2018
Reply
Joint reply filed by intervenor-defendants Wyoming and Montana in support of cross-motion for summary judgment.
11/16/2018
Reply
Reply filed by federal defendants in support of cross-motion for summary judgment.
10/16/2018
Brief
State plaintiffs filed brief in opposition to defendants' and intervenor-defendants' cross-motions for summary judgment and reply in support of motion for summary judgment.
10/16/2018
Reply
Reply brief filed in support of plaintiffs' motion for summary judgment.
09/19/2018
Decision
Intervenor-defendants Wyoming and Montana filed joint memorandum in support of cross-motion for summary judgment and response to plaintiffs' motion for summary judgment.
09/07/2018
Decision
Memorandum filed by federal defendants in support of their cross-motion for summary judgment and opposing plaintiffs' motions for summary judgment.
08/03/2018
Amicus Motion/Brief
Amicus brief filed on behalf of Professor Michael Greenstone.
An economist who is a former co-head of the federal Interagency Working Group on Social Cost of Greenhouse Gases submitted an amicus brief to assist the court in determining whether significant new scientific information justifies requiring supplemental environmental review of the coal leasing program and whether the decision to revoke Secretary Jewell’s order was a major federal action that could significantly affect the environment.
07/27/2018
Brief
Opening brief filed by conservation groups and Northern Cheyenne Tribe in support of plaintiffs' motion for summary judgment.
States, conservation groups, and the Northern Cheyenne Tribe filed motions for summary judgment in their lawsuits challenging the Trump administration’s resumption of the federal coal leasing program and its termination of the programmatic environmental impact review of the program. In March 2017, Secretary of the Interior Ryan Zinke issued Secretarial Order 3348, which revoked Secretarial Order 3338, issued by former Secretary of the Interior Sally Jewell in January 2016. Secretary Jewell’s order commenced the process for the programmatic review and put in place a moratorium on new federal coal leases. The plaintiffs argued that Secretary Zinke’s order was a “major federal action” that required consideration of potential environmental impacts, including climate impacts, under NEPA. The states also argued that the defendants had violated the Mineral Leasing Act, the Federal Land Policy and Management Act, and the Administrative Procedure Act by failing to provide an reasoned explanation for the reversal of the defendants’ prior position that comprehensive review of the federal program was necessary. The conservation groups and Northern Cheyenne Tribe argued that the order violated NEPA by failing to consider impacts to the Tribe and also argued that the defendants violated their trust obligation to the Tribe. The federal defendants’ response and cross-motion for summary judgment is due on September 7.
07/27/2018
Brief
Brief filed by state plaintiffs in support of motion for summary judgment
02/21/2018
Reply
Reply filed by federal defendants in support of motion for partial reconsideration of order requiring supplementation of the administrative record.
02/07/2018
Brief
Brief submitted by plaintiffs in opposition to motion for reconsideration.
01/24/2018
Motion
Motion filed by federal defendants for reconsideration of order requiring supplementation of the administrative record.
12/01/2017
Amicus Motion/Brief
Motion for leave to file an amicus brief filed by Professor Michael Greenstone.
Michael Greenstone, an economist and professor at the University of Chicago and formerly Chief Economist for President Obama's Council of Economic Advisers, requested leave to file an amicus brief to assist the court to make two points: (1) explaining the significance of lifting the coal leasing moratorium without completing an updated environmental review of the federal coal program by demonstrating the societal costs of climate change and air pollution caused by new coal leasing and (2) explaining advances in climate-change economics since the last programmatic review of the coal leasing program in 1979.
12/01/2017
Amicus Motion/Brief
Motion for leave to file amicus curiae brief in support of plaintiffs' motion for summary judgment filed by Institute for Policy Integrity.
11/21/2017
Decision
Plaintiffs' motion to supplement administrative record granted.
06/02/2017
Decision
Motion to consolidate granted.
05/31/2017
Motion
Motion to consolidate filed.
03/29/2017
Complaint
Complaint filed.
Seven environmental organizations and the Northern Cheyenne Tribe filed a lawsuit in the federal district court for the District of Montana challenging the Secretary of the Interior’s decisions to repeal the moratorium on federal coal leasing and to abandon an ongoing programmatic environmental review of the coal leasing program. The Obama administration imposed the moratorium and commenced the review in January 2016. The plaintiffs alleged that the Secretary of the Interior’s actions violated the National Environmental Policy Act because they would allow new coal leasing to occur without a review of the leasing program’s impacts, including climate impacts caused by the burning of coal. The complaint alleged that U.S. Bureau of Land Management (BLM) had completed the original programmatic environmental review of the leasing program in 1979 “at a time when the threat of climate change had not yet been fully realized or understood” and that BLM had never undertaken “a review of whether it can continue its coal leasing program and fulfill its climate commitments, as well as its land-stewardship obligations that are placed in jeopardy by a changing climate.” The plaintiffs contended that the repeal of the moratorium was a major federal action requiring a programmatic environmental impact statement (EIS) or, alternatively, that new information about climate change since 1979 required the preparation of a supplemental programmatic EIS.

Summary

Challenge to lifting of moratorium on federal coal leasing and cessation of programmatic environmental review of leasing program.