Skip to content
The Climate Litigation Database

Friends of the Headwaters v. Minnesota Public Utilities Commission (In re Enbridge Energy, LP)

Geography
Year
2020
Document Type
Litigation
Part of

About this case

Filing year
2020
Status
Petition for review of Court of Appeals decision filed by Red Lake Band of Chippewa Indians et al.
Docket number
A20-1071
Court/admin entity
United StatesState CourtsMinnesota Court of Appeals (Minn. Ct. App.)
Case category
State Law Claims (US)Environmentalist Lawsuits (US)State Law Claims (US)State Impact Assessment Laws (US)
Principal law
United StatesMinnesota Environmental Policy Act
At issue
Challenge to Minnesota Public Utilities Commission authorization of Line 3 pipeline project.
Topics
, ,

Documents

Filing Date
Document
Type
Topics 
Beta
07/14/2021
Petition for review of Court of Appeals decision filed by Red Lake Band of Chippewa Indians et al.
Petition
06/14/2021
Minnesota Public Utilities Commission decisions affirmed.
The Minnesota Court of Appeals upheld the Minnesota Public Utilities Commission’s determination that a revised final environmental impact statement (EIS) for the Line 3 replacement crude oil pipeline was adequate, as well as the Commission’s decisions to issue a certificate of need and a routing permit for the project. The court concluded that it must defer to the Commission’s determination that Enbridge Energy, Limited Partnership demonstrated need for a replacement pipeline because the Commission’s decision was “adequately explained and reasonable, based on the record.” It noted that the Commission “balanced a plethora of factors and criteria … against the backdrop of an existing, deteriorating pipeline” and “based upon a public record developed over multiple years with extraordinary public participation.” Regarding the Commission’s consideration of greenhouse gas emissions and climate change as part of its assessment of the project’s relationship to overall state energy needs, the court rejected the contention that it was arbitrary and capricious not to attach a dollar figure to greenhouse gas emissions from the project. The court found that the Commission adequately explained its rationale for rejecting the dollar figure adopted by the administrative law judge. The court also said it was not arbitrary and capricious for the Commission to reason that the replacement project was not expected to increase crude oil demand. The court also found that the Commission addressed the court’s <a href="https://climatecasechart.com/wp-content/uploads/case-documents/2019/20190603_docket-A18-1283_opinion.pdf">earlier concern</a> that the EIS had not adequately addressed the impact of an oil spill on Lake Superior and its watershed. In addition, the court found that the selection of a pipeline route was reasonable and “based upon respect for tribal sovereignty, while minimizing environmental impacts.” One judge dissented, writing that the certificate of need was unsupported by substantial evidence and based on erroneous interpretations of the governing statute. He agreed with relators that the Commission acted arbitrarily and capriciously by failing to consider the project’s lifecycle greenhouse gas emissions.
Decision
02/02/2021
Motions for a stay denied.
The Minnesota Court of Appeals denied motions to stay the Minnesota Public Utilities Commission’s decisions authorizing Enbridge Energy, LP’s Line 3 pipeline replacement project. The court agreed that one of the movants—Friends of the Headwaters—was precluded from seeking a stay because it had not sought a stay from the Commission. On the merits of the stay motion by the Red Lake Band of Chippewa Indians and White Earth Band of Ojibwe, the court found that the Commission’s denial of a stay was not an abuse of discretion. The court was not persuaded that completion of construction of the pipeline would moot the appeals and concluded both that the Commission was not required to consider whether the appeal raised substantial issues and also that it was not clear that the appeals raised substantial questions that would override other factors to require a stay.
Decision
12/30/2020
Memorandum of relator Friends of the Headwaters in support of motion to stay construction pending appeal.
Decision
12/30/2020
Motion filed by relator Friends of the Headwaters for stay of construction pending appeal.
Motion

Summary

Challenge to Minnesota Public Utilities Commission authorization of Line 3 pipeline project.

 Topics mentioned most in this case  
Beta

See how often topics get mentioned in this case and view specific passages of text highlighted in each document. Accuracy is not 100%. Learn more

Group
Topics
Policy instrument
Risk
Impacted group
Just transition
Renewable energy
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance