Challenge to fill permit for wetlands in National Petroleum Reserve in Alaska for drilling site.
- Climate Litigation Database
- /
- Search
- /
- United States of America
- /
- Kunaknana v. United States Army Corps of Engineers
Kunaknana v. United States Army Corps of Engineers
Geography
Year
2013
Document Type
Litigation
Part of
About this case
Filing year
2013
Status
Settlement reached and fees petition withdrawn.
Geography
Docket number
3:13-cv-00044
Court/admin entity
United States → United States Federal Courts → United States District Court for the District of Alaska (D. Alaska)
Case category
Adaptation (US) → Reverse Impact Assessment (US)Federal Statutory Claims (US) → NEPA (US)
Principal law
United States → National Environmental Policy Act (NEPA)
At issue
Challenge to fill permit for wetlands in National Petroleum Reserve in Alaska for drilling site.
Topics
, ,
Documents
Each case in our database can contain one or more documents.
Filing Date
Document
Type
Topics
05/04/2016
Settlement reached and fees petition withdrawn.
On May 4, 2016, the plaintiffs in a lawsuit that succeeded in requiring the United States Army Corps on Engineers to conduct supplemental environmental analysis for a wetlands fill permit in the National Petroleum Reserve withdrew their petition for attorneys’ fees and other costs under the Equal Access to Justice Act. The plaintiffs said that reached an agreement with the federal defendants that settled their request for fees and costs.
Motion
Legal safeguards for vulnerable groupsJust transition
08/27/2015
Petition for costs and fees submitted by plaintiff.
Plaintiffs who challenged issuance of a fill permit for a drill site in the National Petroleum Reserve in Alaska filed a petition for costs and fees under the federal Equal Access to Justice Act (EAJA). The federal district court for the District of Alaska upheld the permit in 2015, but only after it first remanded the proceeding to the United States Army Corps of Engineers (Corps) in 2014 for a reasoned explanation for the Corps’ decision not to conduct a supplemental environmental analysis. The supplemental analysis subsequently conducted by the Corps included a discussion of whether new information about climate change warranted preparation of a supplemental environmental impact statement and concluded that it did not. In their fees petition, the plaintiffs contended that they were prevailing parties for purposes of EAJA because the court was only satisfied that the Corps had satisfied its NEPA obligations after the Corps completed the supplemental analysis required by the court.
Petition
Legal safeguards for vulnerable groupsFinance flowTerrestrial adaptationAgriculture mitigation+ 2 more
05/26/2015
Second order re motions for summary judgment issued.
The federal district court for the District of Alaska upheld the approval by the United States Army Corps of Engineers (Corps) of a permit to fill wetlands in the National Petroleum Reserve in Alaska for development of a drilling site. The Corps prepared a supplemental information report (SIR) after the court held in 2014 that the Corps had not provided a reasoned explanation for its decision not to prepare a supplemental environmental impact statement (SEIS) to update a 2004 EIS. Pursuant to an agreement between the parties and an order of the court, the SIR included a discussion of whether new information about climate change necessitated preparation of an SEIS. The Corps considered both the impact of climate change on the project and the project’s impacts on climate change. The court agreed with plaintiffs that the Corps had conducted “only a minimalist review” of the impacts of climate change. Nevertheless, the court found that this assessment was adequate given the absence of detailed instructions from the court regarding the analysis the Corps should have performed and given that the
plaintiffs had not identified specific climate change information the Corps should have considered. The court also found that the Corps’ determinations that other new information and changes to the project did not require an SEIS were not arbitrary and capricious, and that the Corps had an adequate basis for its determination that the project was the Least Environmentally Damaging Practicable Alternative as required under Section 404 of the Clean Water Act. Judgment was entered for the defendants on May 29, 2015.
Decision
Freshwater adaptationWater adaptationAdaptation/resilienceFossil fuel+ 20 more
07/22/2014
Order re further proceedings issued.
In July, the court issued an order regarding further proceedings in the case. The court opted not to vacate the permit because stopping ongoing construction would have disruptive consequences. On remand, the court directed the Corps to consider post-2004 information on how climate change could affect the project. The court denied the challengers’ request for a public hearing, noting that the National Environmental Policy Act did not require a public hearing for a determination of whether to prepare a supplemental environmental impact statement. The Corps was required to submit its determination on remand by August 27.
Decision
Construction sectorEnergy supply mitigationFossil fuelOil
06/17/2014
Memorandum submitted by ConocoPhillips Alaska, Inc. in support of motion regarding further proceedings.
Decision
Construction sectorFossil fuelBanOil+ 10 more
06/17/2014
Motion filed by ConocoPhillips Alaska, Inc. regarding further proceedings.
The parties to the lawsuit challenging the granting of a wetlands permit to ConocoPhillips Alaska, Inc. by the United States Army Corps of Engineers could not
agree on a course for further proceedings after the federal district court for the District of Alaska ruled that the Corps had not provided an adequate explanation for its decision not to prepare an SEIS. ConocoPhillips requested a remand without vacatur, asking that the remand period be limited to 90 days and that the scope of the remand only include remedying the errors identified by the court in the Corps’ rationale and addressing post-2004 climate change information. The Corps also requested a 90-day limited remand. Plaintiffs, on the other hand, argued that vacatur of the permit was warranted.
Motion
Finance flow
06/17/2014
Defendants' motion regarding additional proceedings submitted.
Motion
Construction sectorEnergy supply mitigationFishing sector
06/17/2014
Submission on further proceedings submitted by plaintiffs.
Motion
Fossil fuelGasCoalConstruction sector+ 13 more
05/27/2014
Plaintiff's motion for summary judgment granted.
Plaintiffs commenced two actions in the federal district court for the District of Alaska alleging that the United States Army Corps of Engineers (Corps) did not comply with NEPA and Section 404 of the Clean Water Act in issuing a permit to fill wetlands in the National Petroleum Reserve in Alaska. The permit was required for ConocoPhillips Alaska, Inc. to develop a drill site. The court ruled that the Center for Biological Diversity did not have standing to bring the action. In the other action, the court granted partial summary judgment to the plaintiffs to the extent of finding that the Corps had not provided a reasoned explanation for its decision not to conduct a supplemental environmental analysis. The court did not resolve the Clean Water Act claim and asked the parties to conduct briefing on how the action should proceed. Among the issues the court will consider after further briefing is the extent to which the Corps should consider new information about the potential impacts of climate change on the project.
Decision
Fossil fuelOilExtreme weatherGas+ 25 more
Summary
Topics mentioned most in this case
See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.
Group
Topics
Policy instrument
Risk
Impacted group
Just transition
Fossil fuel
Greenhouse gas
Economic sector
Adaptation/resilience
Finance