Skip to content
The Climate Litigation Database
Litigation

Maryland Office of People’s Counsel v. Maryland Public Service Commission

About this case

Documents

Filing Date
Type
Action Taken
Document
Summary
12/15/2015
Decision
Grid resiliency charge upheld.
The Maryland Court of Special Appeals upheld a grid resiliency charge authorized by the Maryland Public Service Commission. The grid resiliency charge would provide $24 million to accelerate “hardening” projects for 24 “feeders” (low-voltage distribution lines that deliver electricity to end users). Potomac Electric Power Company (Pepco) requested approval for the grid resiliency charge in response to recommendations made by a state task force established to address the potential impact of climate change on regional weather patterns and prolonged power outages brought by extreme weather events. The court said that the issue of whether the Commission exceeded its statutory authority when it approved the grid resiliency charge was not properly before the court because it was not raised before the Commission. The court also concluded that the Commission did not act arbitrarily in approving the charge and that there was substantial evidence that the charge was just and reasonable.

Summary

Challenge to grid resiliency charge authorized by Maryland Public Service Commission.