Individuals, solar installation firms, and community organizations coordinated by Friends of the Earth filed legal challenges when the Secretary of State for Energy and Climate Change proposed a downward revision in the rate at which recipients of a feed-in-tariff (FIT) for solar photovoltaic (PV) would be compensated. Their challenge focused not on the rate reduction per se, but its retroactive implementation for generators who installed solar PV facilities after December 2011 but before April 2012. That is, the suit challenged the Secretary’s proposal that those generators begin receiving reduced compensation for electricity generation when the new, lower FIT rate took effect on April 1, 2012.
Some background on the scheme is helpful for understanding the Secretary’s reasons for seeking to push through a rate reduction hastily. The scheme was launched in April 2010 to encourage “small-scale low-carbon generators” to develop more electricity generating capacity using solar PV, wind, and biomass. Electricity suppliers paid the cost of the FIT and passed it on to electricity consumers. Twice the expected volume of new solar PV capacity was installed over the scheme’s first 18 months. In light of this and of falling solar PV costs, the Secretary undertook a fast-tracked review of the FIT rate and proposed to revise it downward starting in April 2012, and to compensate all solar PV generators who installed after December 2011 at the reduced rate from April 2012 on. When the review began, there was a surge in solar PV installations, presumably by people who recognized that the window for securing an advantageous FIT rate would soon close. The Secretary’s proposed rate reduction thus sought to address both to the unexpectedly high volume of solar PV installation overall and to the surge in installations in advance of the higher rate’s sunset.
The appellate court upheld the decision and the reasoning of the lower court, which had reviewed the purpose of the Energy Act 2008 on which the FIT scheme was based and the scope of discretion afforded to the Secretary under that Act. The appellate decision explained that rates fixed for a 25-year period starting with the first day of generation are basic to the FIT scheme, and that the scheme makes no provision for adjusting those rates in the way proposed by the Secretary. FIT rates, the court concluded, may be adjusted in prospect, making it permissible for the Secretary to reduce rates for installations coming online after April 1, 2012, but not in retrospect.
- Climate Litigation Database
- /
- Search
- /
- United Kingdom
- /
- Secretary of State for Energy and Climate Change v. Friends of the Earth
Secretary of State for Energy and Climate Change v. Friends of the Earth
About this case
Filing year
2011
Status
Decided; lower court affirmed
Geography
Court/admin entity
United Kingdom → England and Wales
Case category
Suits against governments (Global) → GHG emissions reduction and trading (Global) → Other (Global)
Principal law
United Kingdom → Energy Act 2008
Topics
, ,
Documents
Each case in our database can contain one or more documents.
Filing Date
Document
Type
Topics
01/25/2012
Individuals, solar installation firms, and community organizations coordinated by Friends of the Earth filed legal challenges when the Secretary of State for Energy and Climate Change proposed a downward revision in the rate at which recipients of a feed-in-tariff (FIT) for solar photovoltaic (PV) would be compensated. Their challenge focused not on the rate reduction per se, but its retroactive implementation for generators who installed solar PV facilities after December 2011 but before April 2012. That is, the suit challenged the Secretary’s proposal that those generators begin receiving reduced compensation for electricity generation when the new, lower FIT rate took effect on April 1, 2012.
Some background on the scheme is helpful for understanding the Secretary’s reasons for seeking to push through a rate reduction hastily. The scheme was launched in April 2010 to encourage “small-scale low-carbon generators” to develop more electricity generating capacity using solar PV, wind, and biomass. Electricity suppliers paid the cost of the FIT and passed it on to electricity consumers. Twice the expected volume of new solar PV capacity was installed over the scheme’s first 18 months. In light of this and of falling solar PV costs, the Secretary undertook a fast-tracked review of the FIT rate and proposed to revise it downward starting in April 2012, and to compensate all solar PV generators who installed after December 2011 at the reduced rate from April 2012 on. When the review began, there was a surge in solar PV installations, presumably by people who recognized that the window for securing an advantageous FIT rate would soon close. The Secretary’s proposed rate reduction thus sought to address both to the unexpectedly high volume of solar PV installation overall and to the surge in installations in advance of the higher rate’s sunset.
The appellate court upheld the decision and the reasoning of the lower court, which had reviewed the purpose of the Energy Act 2008 on which the FIT scheme was based and the scope of discretion afforded to the Secretary under that Act. The appellate decision explained that rates fixed for a 25-year period starting with the first day of generation are basic to the FIT scheme, and that the scheme makes no provision for adjusting those rates in the way proposed by the Secretary. FIT rates, the court concluded, may be adjusted in prospect, making it permissible for the Secretary to reduce rates for installations coming online after April 1, 2012, but not in retrospect.
Decision
Energy supply mitigationRenewable energySolar energyFeed-in-tariff+ 12 more
Summary
Topics mentioned most in this case
See how often Topics get mentioned in this case and view specific passages of text highlighted in each document.
Group
Topics
Policy instrument
Just transition
Renewable energy
Fossil fuel
Economic sector
Finance