Skip to content
The Climate Litigation Database
Litigation

Greenidge Generation LLC v. New York State Department of Environmental Conservation

About this case

Documents

Filing Date
Type
Action Taken
Document
Summary
11/14/2024
Decision
Petition granted in part and denied in part and DEC decision annulled and remitted to DEC for further proceedings.
A New York trial court vacated the New York State Department of Environmental Conservation’s (DEC’s) denial of an application to renew an air permit for a power plant used for behind-the-meter cryptocurrency mining. DEC’s final denial concluded that the facility’s operation would be inconsistent or interfere with attainment of Climate Leadership and Community Protection Act (CLCPA) statewide greenhouse gas emissions limits. The court found that DEC had authority under New York’s Uniform Procedure Act to deny applications for inconsistency with the CLCPA’s standards but that DEC’s denial in this case was arbitrary and capricious and affected by an error of law because the agency stopped its analysis at a finding of inconsistency with the emissions limits and did not assess the justification for the project. The court therefore annulled the final denial and remitted to DEC. The court rejected, however, the applicant’s contention that DEC had engaged in improper policymaking by deciding “behind closed doors” that electricity use for cryptocurrency mining was not desirable. The court also upheld DEC’s determination that granting the renewal application would be inconsistent with attainment of the greenhouse gas emissions limits. In addition, the court found that the applicant did not exhaust its administrative remedies for a Supremacy Clause argument that federal regulation superseded CLCPA obligations.
08/20/2024
Motion
Memorandum of law filed in support of its motion for a temporary restraining order and preliminary injunction.
08/15/2024
Petition
Memorandum of law filed in support of verified petition and complaint.
08/15/2024
Petition
Verified petition and complaint filed.
The operator of a natural gas-fired power plant in Yates County, New York filed a lawsuit in New York Supreme Court challenging the New York State Department of Environmental Conservation’s (DEC’s) denial of its application to renew its Clean Air Act Title V operating permit. The operator asserted that DEC lacked authority under New York’s Climate Leadership and Community Protection Act (CLCPA) to deny the permit based on DEC’s determination that the application would be inconsistent or interfere with statewide greenhouse gas emission limits. The operator also alleged that DEC misinterpreted the CLCPA not to require that DEC determine whether a justification for the application existed or to identify alternatives and mitigation measures. The complaint alleged that DEC’s interpretation would permit the agency “to function as New York State’s de facto climate czar, determining on an ad hoc subjective basis what facilities should be permitted to operate or be shut down based on climate change considerations alone.” In addition, the operator alleged that the decision was based on DEC’s improper policy determination that the facility’s emissions could never be justified because DEC “disapproved of the end use of the electricity generated by the Facility, namely, behind-the-meter cryptocurrency mining.” The operator also asserted that DEC’s determination that the application would not be consistent with greenhouse gas emissions limits was arbitrary and capricious because the operator had reduced emissions by 70% from 1990 levels and had agreed to further reductions consistent with the law’s 2030 target. The operator also contended that DEC’s interpretation of the CLCPA would violate the Supremacy Clause because the agency’s determination did not comply with the New York Independent System Operator’s federally approved tariff.

Summary

Challenge to the denial of an application for renewal of a Title V air permit for natural gas-fired power plant used to power cryptocurrency mining.